Project 22CE0121
DPWH infrastructure contract
Contract ID:
22CE0121
Fingerprint:
de94bf82e63615…96c9498e2b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 4, 2022 (4 yrs 7 mo ago) · Target/actual end Dec 7, 2022
Description:
CONSTRUCTION OF SLOPE PROTECTION ALONG TALAVERA RIVER, BRGY. SAN JOSE, LICAB, NUEVA ECIJA
Category:
Flood Control and Drainage
Implementing office:
DPWH Nueva Ecija 1st DEO · Region III
Contractor:
AMP 723 CONSTRUCTION CORPORATION (FORMERLY: A.M.P. CONSTRUCTION) · DPWH contractor code 16574
Contract amount:
₱96,500,000.00 (₱96.5M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CE0295 | Jun 2, 2025 | CONSTRUCTION OF ROAD, BARANGAY SAN JOSE, LICAB, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0235 | Apr 2, 2025 | NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LICAB-VICTORIA RD, NUEVA ECIJA | Completed | ₱33.9M |
| 25CE0265 | Apr 2, 2025 | CONSTRUCTION OF ROAD, BARANGAY SANTA MARIA, LICAB, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0105 | Mar 21, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TALAVERA RIVER, BARANGAY SANTA LUCIA OLD, ZARAGOZA, NUEVA ECIJA | Completed | ₱48.5M |
| 25CE0019 | Feb 14, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CAINGIN TABING ILOG, GUIMBA, NUEVA ECIJA | Completed | ₱3.0M |
| 25CE0065 | Feb 14, 2025 | REHABILITATION OF ROAD, BARANGAY POBLACION SUR, LICAB, NUEVA ECIJA | Completed | ₱10.7M |
| 25CE0072 | Feb 14, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LABONG RIVER, BARANGAY SAN JUAN, LICAB, NUEVA ECIJA | Completed | ₱48.5M |
| 24CE0189 | Jul 3, 2024 | NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, TALAVERA - LICAB DIVERSION ROAD, NUEVA ECIJA | Completed | ₱19.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.