Project 22CG0255
DPWH infrastructure contract
Contract ID:
22CG0255
Fingerprint:
c8e1c7173d2625…a99fbbf6b5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 25, 2022 (4 yrs 3 mo ago) · Target/actual end Sep 25, 2022
Description:
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS/ LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF STA. LUCIA ANAC - SAN ISIDRO MATUA ROAD, BARANGAY STA. LUCIA ANAC
Category:
Roads
Implementing office:
DPWH Pampanga 1st DEO · Region III
Contractor:
N-22 CONSTRUCTION AND TRADING · DPWH contractor code 25254
Contract amount:
₱4,635,329.89 (₱4.6M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| f2f6a22bf84b… | Jul 14, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PAMPANGA 1ST DEO | ₱4,635,329.89 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CG0176 | Jun 24, 2025 | CONCRETING OF CADUANG TETE TO BRGY. SAPLAD DAVID FARM-TO-MARKET ROAD, BRGY. CADUANG TETE AND BRGY. SAPLAD DAVID, MACABEBE PAMPANGA | Completed | ₱4.7M |
| 25CG0087 | May 22, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD WITH SLOPE PROTECTION WORKS, SITIO PENA, BARANGAY SUA, MASANTOL, PAMPANGA | Completed | ₱93.8M |
| 25CG0088 | May 22, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUBLIC BUIDLINGS / FACULTIES - REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER (PHASE I) AT BARANGAY CONSUELO, MACABEBE, | On-Going | ₱140.3M |
| 25CC0297 | Mar 21, 2025 | CONSTRUCTION OF REVETMENT AT BARANGAY SANTA LUCIA, CALUMPIT, BULACAN | On-Going | ₱37.7M |
| 25CG0025 | Feb 28, 2025 | FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, (DOWNSTREAM- RIGHT BANK) BARANGAY CONSUELO, MACABEBE, PAMP | Completed | ₱46.5M |
| 25CG0029 | Feb 21, 2025 | FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PROTECTION DIKE ALONG PAMPANGA RIVER, BARANGAY CONSUELO, MACABEBE, PAMPANGA | On-Going | ₱93.2M |
| 25CC0123 | Feb 10, 2025 | REHABILITATION OF ROAD, BARANGAY MEYTO, CALUMPIT, BULACAN | Completed | ₱9.7M |
| 24CG0308 | Sep 13, 2024 | BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION/ REHABILITATION OF MULTI-PURPOSE BUILDING, MACABEBE, PAMPANGA | Completed | ₱9.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.