Project 22CH0090
DPWH infrastructure contract
Contract ID:
22CH0090
Fingerprint:
5ceeebfb14e6a7…2b2a7a97e3 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 8, 2022 (4 yrs 5 mo ago) · Target/actual end Nov 4, 2022
Description:
CONCRETING OF GUTAD FMR, BRGY. GUTAD, FLORIDABLANCA, PAMPANGA
Category:
Roads
Implementing office:
DPWH Pampanga 2nd DEO · Region III
Contractor:
M A M CONSTRUCTION & TRADING (FOR. MAM CONST.) · DPWH contractor code 19915
Contract amount:
₱19,893,826.15 (₱19.9M)
Funding source:
Outside Infra - GAA 2022 DA FMR
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CH0063 | Jul 9, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM RAINWATER COLLECTOR SYSTEM, 2ND DISTRICT, PAMPANGA | Completed | ₱2.6M |
| 25CH0038 | Apr 10, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG PORAC RIVER, ASCOMO SECTION, GUAGUA, PAMPANGA | Completed | ₱24.5M |
| 25CH0052 | Apr 10, 2025 | FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG PORAC RIVER, VALDEZ SECTION FLORIDABLANCA, PAMPANGA | Completed | ₱29.4M |
| 24CH0160 | Apr 7, 2025 | REPAIR AND MAINTENANCE OF DAMAGED ROAD SLOPE PROTECTION ALONG CAULAMAN RIVER, DAMPE, FLORIDABLANCA, PAMPANGA | Completed | ₱28.9M |
| 25CH0041 | Apr 7, 2025 | CONSTRUCTION OF ROAD, BARANGAY CALANTAS, FLORIDABLANCA, PAMPANGA | Completed | ₱4.9M |
| 25CH0045 | Apr 7, 2025 | CONSTRUCTIO OF ROAD WITH LINED CANAL, BARANGAY LIGAYA, PULUNGMASLE, GUAGUA, PAMPANGA | Completed | ₱4.9M |
| 25CH0048 | Apr 7, 2025 | CONSTRUCTION OF ROAD, PHASE 2, PUROK 6, BARANGAY PAGUIRUAN, FLORIDABLANCA, PAMPANGA | Completed | ₱4.9M |
| 25CH0049 | Apr 7, 2025 | CONSTRUCTION OF ROAD, BARANGAY DAMPE, FLORIDABLANCA, PAMPANGA, PHASE 2 FLORIDABLANCA, PAMPANGA | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.