Project 22CJ0003
DPWH infrastructure contract
Contract ID:
22CJ0003
Fingerprint:
dcc5e725ba5034…5f0943d62f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 22, 2022 (4 yrs 8 mo ago) · Target/actual end May 24, 2022
Description:
FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CAMILING RIVER LEFT BANK, PINDANGAN 1ST SECTION (PHASE IV), PINDANGAN 1ST, CA
Category:
Flood Control and Drainage
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
ROYAL CROWN MONARCH CONSTRUCTION & SUPPLIES CORP. · DPWH contractor code 09036
Contract amount:
₱51,854,275.06 (₱51.9M)
Funding source:
Regular Infra - GAA 2022 OO-2
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3956ad22545e… | Feb 11, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 1ST DEO | ₱51,854,275.06 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26CJ0075 | Jun 30, 2026 | REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS PANIQUI-CAMILING-WAWA RD - K0170 + 162 - K0171 + 190 | On-Going | ₱25.4M |
| 25CJ0233 | Jun 20, 2025 | CONSTRUCTION OF CAMILING - BAYAMBANG DIVERSION ROAD (SEGMENT 2), CAMILING, TARLAC | Completed | ₱96.5M |
| 25CJ0234 | Jun 20, 2025 | CONSTRUCTION OF CAMILING - BAYAMBANG DIVERSION ROAD (SEGMENT 3), CAMILING, TARLAC | On-Going | ₱95.3M |
| 25CJ0240 | Jun 20, 2025 | CONSTRUCTION OF STA. IGNACIA - CAMILING DIVERSION ROAD (SEGMENT 5), TARLAC | Completed | ₱96.5M |
| 25CJ0285 | May 22, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (CAMILING PUBLIC MARKET), CAMILING, TARLAC (PACKAGE C) | On-Going | ₱97.8M |
| 25CJ0175 | Apr 8, 2025 | PREVENTIVE MAINTENANCE ROMULO H-WAY - K0152+ 562 - K0154 + 007 | Completed | ₱96.5M |
| 25CJ0177 | Apr 8, 2025 | PREVENTIVE MAINTENANCE PANIQUI-CAMILING-WAWA RD - K0167 + 135 - K0168 + 440 | Completed | ₱96.5M |
| 25CJ0230 | Apr 8, 2025 | REHABILITATION OF CAMILING ROAD NETWORK (ANNEX 3), CAMILING, TARLAC | Completed | ₱96.5M |