Hashed input (canonical JSON of the source row)
["dpwh","22CJ0016","FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAMILING RIVER, LEFT BANK, PAO 3RD-PAO 2ND SECTION (PACKAGE A), CAMILING,","Flood Control and Drainage","Completed",48016173.68,0,100,"Tarlac DEO","Region III","R.R. RICAFORT CONSTRUCTION AND SUPPLIES (14402)","2022-01-28","2022-06-07",2022,"Regular Infra - GAA 2022 OO-2",15.7091,120.42046,"306903000","306900000"]
SHA-256
a4d3ab33e4308267d2de2a1095e0761e60e889a8f475ecf7c7d162b50b30371b

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.