Project 22CJ0019
DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","22CJ0019","FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CAMILING RIVER RIGHT BANK, BILAD-SAWAT SECTION, CAMILING, TARLAC","Flood Control and Drainage","Completed",89841500,0,100,"Tarlac DEO","Region III","ROYAL CROWN MONARCH CONSTRUCTION & SUPPLIES CORP. (09036)","2022-02-22","2022-05-18",2022,"Regular Infra - GAA 2022 OO-2",15.71658,120.42704,"306903000","306900000"]
SHA-256
fc90543931f243df15f28e1d83f692b1ff3003c3690c7c1ebed572beb3a36c49Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.