Project 22CK0087
DPWH infrastructure contract
Contract ID:
22CK0087
Fingerprint:
1b580d203de917…d9785fd7d8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 26, 2022 (4 yrs 7 mo ago) · Target/actual end Dec 29, 2022
Description:
REHABILITATION/IMPROVEMENT OF EXISTING DIKE ALONG LUCUNG RIVER, U/S OF SANTIAGO BRIDGE, LEFT BANK, STA. 5+878.20 TO STA. 5+312.20, CONCEPCION, TARLAC
Category:
Flood Control and Drainage
Implementing office:
DPWH Tarlac 2nd DEO · Region III
Contractor:
11-16 CONSTRUCTION · DPWH contractor code 29646
Contract amount:
₱95,657,621.00 (₱95.7M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 58b3514fef45… | Mar 23, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 2ND-DEO | ₱94,497,675.28 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CK0137 | Aug 20, 2025 | EMERGENCY REHABILITATION/RECONSTRUCTION OF EXISTING DIKE ALONG LUCUNG RIVER (MALUPA SECTION) DS OF LUCUNG BRIDGE, LEFT BANK, BRGY. MALUPA, CONCEPCION, TARLAC - PACKAGE C | Completed | ₱42.9M |
| 25CK0126 | Jun 13, 2025 | CONSTRUCTION OF SCHOOL BUILDING, MAGAO HIGH SCHOOL, BARANGAY MAGAO, CONCEPCION, TARLAC | Completed | ₱19.9M |
| 25CK0125 | May 20, 2025 | CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - RAIN WATER COLLECTORS IN PUBLIC FACILITIES WITHIN 3RD LEGISLATIVE DISTRICT OF TARLAC, CONCEPCION, TARLAC | Completed | ₱2.6M |
| 25CK0075 | Apr 3, 2025 | REHABILITATION OF ROAD, LILIBANGAN - CASTILLO ROAD, CONCEPCION, TARLAC | Completed | ₱49.0M |
| 25CK0076 | Apr 3, 2025 | REHABILITATION OF ROAD AT BARANGAY LILIBANGAN TO CASTILLO ROAD, CONCEPCION, TARLAC | Completed | ₱96.5M |
| 25CK0083 | Apr 3, 2025 | REHABILITATION OF ROAD AT BARANGAY CASTILLO, CONCEPCION, TARLAC | Completed | ₱49.0M |
| 25CK0084 | Apr 3, 2025 | REHABILITATION OF ROAD AT BARANGAY SAN VICENTE, CONCEPCION, TARLAC | On-Going | ₱49.0M |
| 25CK0085 | Apr 3, 2025 | ASSET PRESERVATION PROGRAM: PREVENTIVE MAINTENANCE - TERTIARY ROADS ALONG CONCEPCION - LA PAZ ROAD, K0124+000.00 TO K0126+000.00, CONCEPCION, TARLAC | Completed | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.