Project 22CL0002
DPWH infrastructure contract
Contract ID:
22CL0002
Fingerprint:
10d87fbc8ea9d0…5b4a1bebdd Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 23, 2022 (4 yrs 8 mo ago) · Target/actual end Apr 25, 2022
Description:
RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, MACULCOL BR. (B01393LZ) ALONG OLONGAPO-BUGALLON RD, SAN NARCISO, ZAMBALES
Category:
Bridges
Implementing office:
DPWH Zambales 1st DEO · Region III
Contractor:
ALPHATEC CHEMICAL CORPORATION · DPWH contractor code 39938
Contract amount:
₱91,491,241.00 (₱91.5M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CL0256 | Jul 18, 2025 | CONSTRUCTION OF FLOOD CONTROL RIVERBANK STRUCTURE ALONG SANTO TOMAS RIVER (OMAYA-BALINGCAGUING-PAITE SECTION), SAN NARCISO, ZAMBALES (PHASE 1) | On-Going | ₱48.8M |
| 25CL0257 | Jul 18, 2025 | CONSTRUCTION OF FLOOD CONTROL RIVERBANK STRUCTURE ALONG SANTO TOMAS RIVER (OMAYA-BALINGCAGUING-PAITE SECTION), SAN NARCISO, ZAMBALES (PHASE 2) | On-Going | ₱48.8M |
| 25CL0135 | Jun 6, 2025 | CONSTRUCTION OF ROAD, PUROK 1, BARANGAY DALLIPAWEN, SAN NARCISO, ZAMBALES | On-Going | ₱19.4M |
| 25CL0188 | May 23, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING, SAN JOSE PATROCINIO ELEMENTARY SCHOOL, SAN NARCISO, ZAMBALES | On-Going | ₱14.7M |
| 25CL0192 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 1, SAN NARCISO, ZAMBALES | On-Going | ₱96.4M |
| 25CL0193 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 2, SAN NARCISO, ZAMBALES | On-Going | ₱96.5M |
| 25CL0194 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 3, SAN NARCISO, ZAMBALES | On-Going | ₱96.4M |
| 25CL0195 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 4, SAN NARCISO, ZAMBALES | On-Going | ₱96.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.