Project 22CL0021
DPWH infrastructure contract
Contract ID:
22CL0021
Fingerprint:
adb269f2f06278…46de4817bc Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 2, 2022 (4 yrs 8 mo ago) · Target/actual end Sep 10, 2022
Description:
CONSTRUCTION OF MACULCOL RIVER DIKE, UPSTREAM, NORTH APPROACH, SAN NARCISO, ZAMBALES
Category:
Flood Control and Drainage
Implementing office:
DPWH Zambales 1st DEO · Region III
Contractor:
MCB ZAMORA CONSTRUCTION & SUPPLY · DPWH contractor code 32006
Contract amount:
₱48,999,754.56 (₱49.0M)
Funding source:
Regular Infra - GAA 2022 OO-2
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 751d3253d0ac… | Mar 10, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBALES 1ST DEO | ₱46,793,648.55 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CL0256 | Jul 18, 2025 | CONSTRUCTION OF FLOOD CONTROL RIVERBANK STRUCTURE ALONG SANTO TOMAS RIVER (OMAYA-BALINGCAGUING-PAITE SECTION), SAN NARCISO, ZAMBALES (PHASE 1) | On-Going | ₱48.8M |
| 25CL0257 | Jul 18, 2025 | CONSTRUCTION OF FLOOD CONTROL RIVERBANK STRUCTURE ALONG SANTO TOMAS RIVER (OMAYA-BALINGCAGUING-PAITE SECTION), SAN NARCISO, ZAMBALES (PHASE 2) | On-Going | ₱48.8M |
| 25CL0135 | Jun 6, 2025 | CONSTRUCTION OF ROAD, PUROK 1, BARANGAY DALLIPAWEN, SAN NARCISO, ZAMBALES | On-Going | ₱19.4M |
| 25CL0188 | May 23, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING, SAN JOSE PATROCINIO ELEMENTARY SCHOOL, SAN NARCISO, ZAMBALES | On-Going | ₱14.7M |
| 25CL0192 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 1, SAN NARCISO, ZAMBALES | On-Going | ₱96.4M |
| 25CL0193 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 2, SAN NARCISO, ZAMBALES | On-Going | ₱96.5M |
| 25CL0194 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 3, SAN NARCISO, ZAMBALES | On-Going | ₱96.4M |
| 25CL0195 | May 23, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG STO. TOMAS RIVER (MACULCOL DIKE) SOUTH APPROACH, PHASE 4, SAN NARCISO, ZAMBALES | On-Going | ₱96.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.