Project 22DE0073
DPWH infrastructure contract
Contract ID:
22DE0073
Fingerprint:
4ab8fd908419c1…55303b324c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 31, 2022 (4 yrs 7 mo ago) · Target/actual end Nov 28, 2022
Description:
ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - SECONDARY ROADS, LOBO-MALABRIGO-SN JUAN RD - K0160+500 - K0160+740, K0160+874 - K0161+416
Category:
Roads
Implementing office:
DPWH Batangas 2nd DEO · Region IV-A
Contractor:
TCSC CORP. · DPWH contractor code 15453
Contract amount:
₱56,588,565.00 (₱56.6M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a19164374aaa… | Mar 23, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATANGAS 2ND ED | ₱54,890,712.20 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DE0164 | Jul 7, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - SECONDARY ROAD, BATANGAS-LOBO RD - K0133+684 - K0135+000 | On-Going | ₱93.8M |
| 25DE0191 | Jul 7, 2025 | CONCRETING OF BRGY. NAGTALUNTONG FMR (PHASE I), BRGY. NAGTALUNTONG, LOBO, BATANGAS | On-Going | ₱14.9M |
| 25DE0177 | Jun 2, 2025 | CONCRETING OF BRGY. CUMBA FMR, BRGY. CUMBA, BATANGAS CITY, BATANGAS | Completed | ₱14.9M |
| 25DE0179 | Jun 2, 2025 | CONCRETING OF BRGY. BANALO FMR, BRGY. BANALO, LOBO, BATANGAS | On-Going | ₱7.4M |
| 25DE0061 | May 27, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM (WATER WORKS), BARANGAY BALATBAT, LOBO, BATANGAS | On-Going | ₱4.8M |
| 25DE0083 | May 27, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION/ REHABILITATION OF BRGY. ROAD, SITIO KALINGAG, APAR, LOB | On-Going | ₱14.8M |
| 25DE0084 | May 27, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION/ REHABILITATION OF BRGY. ROAD, SITIO MALVAR, SAN NICOLAS | On-Going | ₱14.4M |
| 25DE0114 | May 27, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL AT PUROK 6, BARANGAY MASAGUITSIT, LOBO, BATANGAS | On-Going | ₱1.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.