Project 22DJ0019
DPWH infrastructure contract
Contract ID:
22DJ0019
Fingerprint:
55dd779f573488…2e7c40f555 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 24, 2022 (4 yrs 7 mo ago) · Target/actual end Jul 21, 2022
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, SITIO BUNTOG, BARANGAY SAN MATEO, DOLORES, QUE
Category:
Roads
Implementing office:
DPWH Quezon 2nd DEO · Region IV-A
Contractor:
ROMHEAD S.J. BUILDERS AND DEVELOPMENT INCORPORATED. · DPWH contractor code 39959
Contract amount:
₱4,950,000.00 (₱5.0M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DJ0108 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BULAKIN 2, DOLORES, QUEZON | On-Going | ₱2.4M |
| 25DJ0110 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY KINABUHAYAN, DOLORES, QUEZON | On-Going | ₱4.8M |
| 25DJ0125 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL TRADING CENTER) IN DOLORES, QUEZON | On-Going | ₱4.8M |
| 25DJ0096 | Mar 31, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY ANTONINO, DOLORES, QUEZON | Completed | ₱9.6M |
| 25DJ0009 | Mar 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTA LUCIA, DOLORES, QUEZON | Completed | ₱7.3M |
| 25DJ0032 | Mar 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, MANGGAHAN SCHOOL, BARANGAY MANGGAHAN, DOLORES, QUEZON | Completed | ₱7.3M |
| 25DJ0062 | Mar 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MANGGAHAN, DOLORES, QUEZON | Completed | ₱2.9M |
| 25DJ0078 | Mar 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY PINAGDANLAYAN, DOLORES, QUEZON | On-Going | ₱19.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.