FY2026 GAA: ₱6.79T
PisoScan

Project 22DN0115

DPWH infrastructure contract
Contract ID:
22DN0115
Fingerprint:
7fb3c84c37fb87…c702b7f206 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 13, 2022 (4 yrs 4 mo ago) · Target/actual end Dec 15, 2023
Description:
CONSTRUCTION OF BRIDGE, BRGY. MAMBUGAN AND BRGY. MUNTINDILAW ANTIPOLO CITY (FIRST DISTRICT)
Category:
Bridges
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
F.P. DE GUZMAN CONSTRUCTION, INC. · DPWH contractor code 10296
Contract amount:
₱29,393,449.18 (₱29.4M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
bbd5fb28a967…Jun 30, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL 1ST ED₱28,531,870.46

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DN0108May 29, 2025REHABILITATION OF DRAINAGE ALONG PAROLA STREET, BARANGAY SAN ANDRES CAINTA, RIZAL (FIRST DISTRICT)On-Going₱9.9M
25DN0074May 27, 2025REHABILITATION OF ROAD, BARANGAY MAMBUGAN AND BARANGAY MUNTINDILAW, ANTIPOLO CITY, RIZAL (FIRST DISTRICT)On-Going₱14.4M
25DN0078May 27, 2025REHABILITATION OF ROAD, PHASE 2, BARANGAY MAYAMOT, ANTIPOLO CITY, RIZAL (FIRST DISTRICT)On-Going₱9.6M
25DN0015May 23, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - CAINTA - KAYTICKLING - ANTIPOLO - TERESA - MORONG RD - K0020+402 - K0020+594, K0020+800 - K0019+222, RIZAL (FIRST DISTRICT)Completed₱14.1M
25DN0023May 23, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, HALANG CREEK, PHASE 4, BARANGAY MAYAMOT, ANTIPOLO CITY, RIZAL (FIRST DISTRICT)On-Going₱69.6M
25OB0450May 22, 2025REHABILITATION OF FLOOD MITIGATION STRUCTURE ALONG ILUGIN CREEK, PASIG CITY (PHASE 1)Completed₱47.3M
25D00064May 21, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BALANTI CREEK, CAINTA, RIZALOn-Going₱95.0M
25D00084May 21, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CAINTA RIVER, BARANGAY SAN JUAN, CAINTA, RIZALOn-Going₱94.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.