Project 22E00065
DPWH infrastructure contract
Contract ID:
22E00065
Fingerprint:
735dd66689f61a…9d4a2ac319 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 2, 2022 (4 yrs 2 mo ago) · Target/actual end Mar 9, 2023
Description:
CONSTRUCTION OF TIGUION RIVER FLOOD CONTROL, GASAN, MARINDUQUE (PACKAGE 1), STA. 0+400-STA. 0+540.60 (RS), GASAN, MARINDUQUE
Category:
GAA 2022 OO-2
Implementing office:
DPWH MIMAROPA Region · MIMAROPA Region
Contractor:
SAN SEBASTIAN CONSTRUCTION · DPWH contractor code 51494
Location:
Contract amount:
₱19,299,804.74 (₱19.3M)
Funding source:
Regular Infra - GAA 2022 OO-2
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| ef4fb80465fb… | Aug 22, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION IV-B | ₱18,687,277.28 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EA0102 | Mar 10, 2026 | LAST MILE SCHOOLS PROGRAM - BACONGBACONG ES, GASAN, MARINDUQUE | On-Going | ₱10.8M |
| 25EA0100 | Feb 2, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, BOGNUYAN ES, GASAN, MARINDUQUE | On-Going | ₱8.0M |
| 25EA0018 | Mar 21, 2025 | NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0095+526 - K0097+077, K0097+137 - K0097+812 | Completed | ₱103.0M |
| 25EA0033 | Mar 21, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (PHASE 2), BARANGAY LIBTANGIN, GASAN, MARINDUQUE | Completed | ₱2.9M |
| 25EA0002 | Feb 21, 2025 | FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, CONSTRUCTION OF MASIGA FLOOD CONTROL STRUCTURE, BARANGAY MASIGA, GASAN, MARINDUQUE | Completed | ₱38.8M |
| 24EA0096 | Jan 28, 2025 | SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF TIGUION RIVER CONTROL, GASAN, MARINDUQUE | Completed | ₱48.2M |
| 24EA0063 | Mar 18, 2024 | CONCRETING OF BRGY. BOGNUYAN FMR PHASE II, BRGY. BOGNUYAN, GASAN,MARINDUQUE | Completed | ₱14.9M |
| 24EA0072 | Mar 15, 2024 | CONSTRUCTION OF BAHI-TAPUYAN ROAD, GASAN, MARINDUQUE | Completed | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.