Project 22ED0133
DPWH infrastructure contract
Contract ID:
22ED0133
Fingerprint:
480fbac2569a7a…6131c5ddd6 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 3, 2022 (4 yrs 4 mo ago) · Target/actual end Apr 11, 2023
Description:
CONSTRUCTION/IMPROVEMENT/REHABILITATION/COMPLETION OF VARIOUS MULTI - PURPOSE BUILDINGS (COVERED COURT, BRGY. HALL, EVACUATION CENTER), SOCORRO, ORIENTAL MINDORO
Category:
GAA 2022 CSSP
Implementing office:
DPWH Mindoro Oriental DEO · MIMAROPA Region
Contractor:
DZEE BUILDERS & CONSTRUCTION SUPPLY · DPWH contractor code 36200
As listed: DZEE BUILDERS AND CONSTRUCTION SUPPLY
Contract amount:
₱19,208,039.35 (₱19.2M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| b9b4f7b32200… | Jun 20, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MINDORO ORIENTAL D | ₱19,208,042.55 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ED0105 | May 26, 2025 | PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD - K0046+000 - K0047+462, ORIENTAL MINDORO | Completed | ₱115.8M |
| 25ED0106 | May 26, 2025 | PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD - K0049+000 - K0050+765, ORIENTAL MINDORO | Completed | ₱82.0M |
| 25ED0108 | May 26, 2025 | INSTALLATION OF STREET LIGHTS ALONG CALAPAN SOUTH ROAD K0047+200 - K0060+800, SOCORRO, ORIENTAL MINDORO | Completed | ₱95.1M |
| 25ED0123 | May 26, 2025 | PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD - K0062+000 - K0063+015, ORIENTAL MINDORO | Completed | ₱106.1M |
| 25ED0125 | May 26, 2025 | PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0050+765 - K0052+246, ORIENTAL MINDORO | Completed | ₱86.8M |
| 25ED0126 | May 26, 2025 | PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0052+246 - K0053+511, ORIENTAL MINDORO | On-Going | ₱57.9M |
| 25ED0127 | May 26, 2025 | PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0061+129 - K0062+000, ORIENTAL MINDORO | Completed | ₱72.4M |
| 25ED0134 | May 26, 2025 | REHABILITATION OF BRGY. LEUTEBORO I - BRGY. MATUNGAO ROAD, SOCORRO, ORIENTAL MINDORO | Completed | ₱144.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.