Project 22EH0103

DPWH infrastructure contract
Contract ID:
22EH0103
Fingerprint:
2d8d77b7e9feed…351a9cb941 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 3, 2022 (4 yrs 5 mo ago) · Target/actual end Nov 11, 2022
Description:
CONCRETING OF BRGY. POCTOY FMR, STA. 00+000.00 - STA. 00+365, BRGY. POCTOY, ODIONGAN, ROMBLON
Category:
GAA 2022 DA FMR
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
TABLAS CONSTRUCTION CORPORATION · DPWH contractor code 45015
Contract amount:
₱11,940,000.00 (₱11.9M)
Funding source:
Outside Infra - GAA 2022 DA FMR
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
acbec2b7b4d3…May 19, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ROMBLON DEO₱11,692,564.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26EH0001Jul 9, 2026CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BATIANO, ODIONGAN, ROMBLON (12.4201306 ° N, 121.989187 ° E), ODIONGAN, ROMBLONOn-Going₱8.8M
25EH0061Jul 28, 2025CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG DAPAWAN-TORREL RD, K0002+046 + K0002+691.50 AS PER ACTUAL & RBIA, TABLAS ISLAND, ROMBLONOn-Going₱12.6M
25EH0146Jul 28, 2025CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG TABLAS CIRCUMFERENTIAL RD, K0127+760 - K0127+898.50, K0127+902.90 - K0128+022 AS PER RBIA, K0127+760 - K0127+898.50, K0127+902.90 - K0128+020 AS PER ACTUAL, TABLAS ISLAND, ROMBLONCompleted₱4.9M
25EH0168Jul 28, 2025COMPLETION OF MULTI-PURPOSE BUILDING (UKR) AT BARANGAY TABIN-DAGAT, ODIONGAN, ROMBLONCompleted₱2.0M
25EH0060Jul 25, 2025CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG LOOC (COGON TULAY)-ODIONGAN RD, K0103+315.00 - K0103+563.00 (FIRST SECTION), K0123+300.00 - K0123+402.00 (SECOND SECTION), TABLAS ISLAND, ROMBLONOn-Going₱4.4M
25EH0130Jul 11, 2025CONSTRUCTION OF TUGUIS WATER IMPOUNDING PROJECT, ODIONGAN, ROMBLONOn-Going₱48.0M
25EH0110Jul 10, 2025CONSTRUCTION OF REVETMENT STRUCTURE ALONG PATO-O RIVER, ODIONGAN, ROMBLONOn-Going₱139.7M
25EH0111Jul 10, 2025CONSTRUCTION OF REVETMENT STRUCTURE ALONG PATO-O RIVER (PHASE 2), ODIONGAN, ROMBLONOn-Going₱139.8M