FY2026 GAA: ₱6.79T
PisoScan

Project 22EH0114

DPWH infrastructure contract
Contract ID:
22EH0114
Fingerprint:
8d2e54740260d4…7913947286 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 27, 2022 (4 yrs 4 mo ago) · Target/actual end Oct 20, 2022
Description:
CONCRETING OF BRGY. TUGUIS FMR, STA. 00+310.00 - STA. 00+660.00, BRGY. TUGUIS, LOOC, ROMBLON
Category:
GAA 2022 DA FMR
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
EMQ DESIGN & CONSTRUCTION · DPWH contractor code 16128
Contract amount:
₱11,885,835.89 (₱11.9M)
Funding source:
Outside Infra - GAA 2022 DA FMR
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
b9a8d69f5344…May 30, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ROMBLON DEO₱11,598,007.38

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26EH0032Aug 11, 2026REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - LOOC (COGON TULAY) - ODIONGAN RD - K0103+198-K0103+330.70, K0103+338.56 - K0103+362.50, TABLAS ISLAND, ROMBLONOn-Going₱4.4M
25EH0084Jul 28, 2025ROAD WIDENING ALONG TABLAS CIRCUMFERENTIAL ROAD, K0098+820.00-K0099+202.90, K0099+231.13 - K0100+350.23 (AS PER ACTUAL), K0098+820.00-K0099+199.90, K0099+231.13 - K0100+341.23 (AS PER RBIA), TABLAS ISLAND, ROMBLONOn-Going₱96.2M
25EH0129Jul 10, 2025CONSTRUCTION OF LIMON NORTE WATER IMPOUNDING PROJECT, LOOC, ROMBLONOn-Going₱48.0M
25EH0155May 27, 2025CONSTRUCTION OF ROAD, PHASE 2, BARANGAY BAGSIK - SITIO LOBTON TO BARANGAY MADALAG (ALCANTARA) LEADING TO BARANGAY TUGUIS, LOOC, ROMBLONOn-Going₱93.6M
25EH0158May 27, 2025CONSTRUCTION OF BRGY. PILI TO BRGY. LIMON SUR ROAD (PHASE 2), LOOC, ROMBLONOn-Going₱119.9M
25EH0022May 26, 2025CONSTRUCTION OF CAUSEWAY ALONG PUNTA, LOOC, ROMBLON, TABLAS ISLAND, ROMBLONOn-Going₱71.3M
25EH0109May 26, 2025COMPLETION OF MULTI-PURPOSE BUILDING (GOVERNMENT CENTER) AT BARANGAY PUNTA, LOOC, ROMBLONOn-Going₱9.7M
25EH0114May 26, 2025COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY TUGUIS, LOOC, ROMBLONCompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.