Project 22EH0171
DPWH infrastructure contract
Contract ID:
22EH0171
Fingerprint:
337f829d399ce1…7b74801a58 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 9, 2023 (3 yrs 9 mo ago) · Target/actual end Jul 10, 2023
Description:
CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOM UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUNDS (BEFF) - BATCH 2, 1STY2CL, CONCEPCION SUR ES, SANTA MARIA, ROMBLON
Category:
GAA 2022 DepEd BEFF
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
TRIPLE PEAK MOUNTAIN CONSTRUCTION AND SUPPLY · DPWH contractor code 43000
As listed: TRIPLE PEAK MOUNTAIN CONSTRUCTION & SUPPLY
Contract amount:
₱3,919,869.51 (₱3.9M)
Funding source:
Outside Infra - GAA 2022 DepEd BEFF
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a3ee279b6eac… | Jan 17, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ROMBLON DEO | ₱3,919,869.51 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26EH0047 | Aug 20, 2026 | RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - SECONDARY ROADS - AGBUNYOG BR. (B00037TL) ALONG TABLAS CIRCUMFERENTIAL ROAD, TABLAS ISLAND, ROMBLON | On-Going | ₱17.6M |
| 25EH0178 | Apr 20, 2026 | LAST MILE SCHOOLS PROGRAM - TALAMBAN ELEMENTARY SCHOOL, SANTA MARIA (IMELDA), ROMBLON | On-Going | ₱20.7M |
| 25EH0125 | May 26, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY BONGA, STA. MARIA, ROMBLON | Completed | ₱3.9M |
| 25E00137 | Feb 15, 2025 | CONSTRUCTION OF MISSING LINKS/NEW ROADS- ODIONGAN EAST-WEST ROAD, ODIONGAN, ROMBLON | On-Going | ₱139.7M |
| 24EH0127 | Apr 15, 2024 | CONSTRUCTION OF ROAD, SITIO AGCALATAO TO BARANGAY CONCEPCION, STA. MARIA, ROMBLON | Completed | ₱125.4M |
| 24EH0021 | Mar 12, 2024 | CONSTRUCTION OF ROAD, SITIO TUBURAN LEADING TO AGCALATAO ROAD, BARANGAY CONCEPCION PHASE 2, STA. MARIA, ROMBLON | Completed | ₱144.7M |
| 24E00195 | Mar 9, 2024 | SUSTAINABLE INFRASTRUCTRE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COPASTAL ROAD, PHASE 2, STA. MARIA, TABLAS ISLAND, ROMBLON | On-Going | ₱241.2M |
| 24EH0050 | Feb 14, 2024 | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG TABLAS CIRCUMFERENTIAL ROAD, K0069+853 - K0070+128 AS PER ACTUAL, K0069+853 - K0070+115 AS PER RBIA, TABLAS ISLAND, ROMBLON | Completed | ₱13.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.