Project 22FG0062
DPWH infrastructure contract
Contract ID:
22FG0062
Fingerprint:
b7c02c532c2c98…eab9ee3bc6 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 25, 2022 (4 yrs 5 mo ago) · Target/actual end Jun 12, 2023
Description:
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (SEAWALL) ALONG LAMIT BAY STA.0+000.00 - STA.0+678.00 BARANGAY SIPACO, LAGONOY, CAMARINES SUR
Category:
Flood Control and Drainage
Implementing office:
DPWH Camarines Sur 4th DEO · Region V
Contractor:
E.A. SANCHO CONST. INC. (FORM. E.A. SANCHO CONST.) · DPWH contractor code 5648
Contract amount:
₱49,000,000.00 (₱49.0M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25FG0099 | Jul 8, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, LAGONOY, CAMARINES SUR | On-Going | ₱47.5M |
| 25FG0068 | Jun 26, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (DRAINAGE SYSTEM) BARANGAY SAN RAFAEL TO SAN ISIDRO SUR HIGHWAY), LAGONOY, CAMARINES SUR | On-Going | ₱4.7M |
| 25FG0051 | Jun 25, 2025 | CONSTRUCTION OF ROAD WITH DRAINAGE ALONG TIGAON-GOA-SAN JOSE-LAGONOY-GUIJALO VIA SAN VICENTE ROAD, BARANGAY SAN RAFAEL SECTIONLAGONOY, CAMARINES SUR | On-Going | ₱9.4M |
| 25FG0030 | Apr 4, 2025 | CONSTRUCTION OF MISSING LINKS/NEW ROADS, LALUD-GARCHITORENA ROAD (DEL CARMEN SECTION), CAMARINES SUR, LAGONOY, CAMARINES SUR | On-Going | ₱65.4M |
| 25FG0029 | Mar 31, 2025 | CONSTRUCTION OF DRAINAGE CANAL AT CRIS, LAGONOY, CAMARINES SUR | On-Going | ₱9.6M |
| 25FG0032 | Mar 31, 2025 | CONSTRUCTION OF DRAINAGE CANAL AT CRIS, BARANGAY LOHO, LAGONOY, CAMARINES SUR | On-Going | ₱14.4M |
| 25F00127 | Mar 12, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGO | On-Going | ₱159.0M |
| 25F00128 | Mar 12, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGO | On-Going | ₱154.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.