Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 22G00102

DPWH infrastructure contract
Contract ID:
22G00102
Fingerprint:
2193b39c532786…642092df46 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 3, 2022 (4 yrs 8 mo ago) · Target/actual end Jun 29, 2022
Description:
CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MINAPASUK, CALATRAVA, NEGROS OCCIDENTAL
Category:
Buildings and Facilities
Implementing office:
DPWH Region VI · Region VI
Contractor:
KENBE CONSTRUCTION & SUPPLY · DPWH contractor code 34290
Contract amount:
₱1,980,000.00 (₱2.0M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
eb132b2640d8…Feb 23, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION VI₱1,920,571.01

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26RE0046Aug 3, 2026REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS ALONG BACOLOD NORTH RD. K0111+851 - K0111+977On-Going₱22.0M
26RE0047Aug 3, 2026ROAD WIDENING ALONG BACOLOD NORTH RD - K0124 + 238 - K0125 + 000On-Going₱31.7M
26RE0044Jul 13, 2026REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, DA-AN LUNSOD BR. (B00179NR) ALONG BACOLOD NORTH RDOn-Going₱5.3M
26RE0034Jun 29, 2026ROAD WIDENING ALONG BACOLOD NORTH RD - K0130 + 453 - K0130 + 919, K0132 + 233 K0132 + 904, K0153 + 056 - K0153 + 281, K0153 + 453 - K0153 + 483, K0156 + 501 - K0156 + 631On-Going₱36.1M
26RE0038Jun 29, 2026PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY ALONG BACOLOD NORTH RD - K0118 + 531 - K0119 + 718On-Going₱55.7M
25RE0034Jun 26, 2026ROAD WIDENING ALONG BACOLOD NORTH RD (S00425NR) K0117 + 739 K0118 + 290, K0118 + 398 K0118 + 531On-Going₱18.3M
26RE0024Jun 15, 2026RECONSTRUCTION TO CONCRETE PAVEMENT ALONG BACOLOD NORTH RD - K0099+916 - K0100+125On-Going₱5.2M
26RE0011May 20, 2026REHABILITATION/ MAJOR REPAIR OF ROAD SLOPE PROTECTION STRUCTURE ALONG BACOLOD NORTH RD. K0096+942 - K0097+042, K0102+796 - K0102+814On-Going₱4.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.