Project 22GA0016
DPWH infrastructure contract
Contract ID:
22GA0016
Fingerprint:
6e0296baa7d709…14fbc0e5d2 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 4, 2022 (4 yrs 9 mo ago) · Target/actual end Jun 8, 2022
Description:
OFF-CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDER ALONG AKLAN WEST ROAD (KALIBO NABAS) (S00324PN) K0267+890 K0271+365 AKLAN WEST ROAD (KALIBO-NABAS)
Category:
Roads
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
SOLID MERCHANDISING · DPWH contractor code 31609
Contract amount:
₱28,829,115.48 (₱28.8M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 243254b40441… | Jan 20, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO | ₱28,829,115.48 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GA0133 | Jul 22, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AKLAN RIVER, BARANGAY CAMANCI NORTE, NUMANCIA, AKLAN | On-Going | ₱88.3M |
| 25GA0095 | Jun 3, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY LAGUINBANUA WEST, NUMANCIA, AKLAN | On-Going | ₱2.0M |
| 25GA0097 | Jun 3, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY PUSIW, NUMANCIA, AKLAN | On-Going | ₱2.0M |
| 25GA0099 | Jun 3, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY BULWANG, NUMANCIA, AKLAN | Completed | ₱2.4M |
| 25GA0116 | Jun 3, 2025 | CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY DONGON EAST, NUMANCIA, AKLAN | On-Going | ₱3.0M |
| 25GA0139 | Jun 3, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY JOYAO JOYAO, NUMANCIA, AKLAN | On-Going | ₱2.0M |
| 25GA0098 | May 23, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY NAVITAS, NUMANCIA, AKLAN | On-Going | ₱3.7M |
| 25GA0117 | May 23, 2025 | CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY MARIANOS, NUMANCIA, AKLAN | On-Going | ₱2.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.