Project 22GA0155
DPWH infrastructure contract
Contract ID:
22GA0155
Fingerprint:
b98b60b7070565…537e6dccd5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 11, 2023 (3 yrs 10 mo ago) · Target/actual end Dec 5, 2023
Description:
CONCRETING OF TAGAROROC TO UNIDOS FMR, NABAS, AKLAN
Category:
Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - PCCP
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
EC BUILDERS · DPWH contractor code 47417
Contract amount:
₱19,873,400.01 (₱19.9M)
Funding source:
Outside Infra - Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Construction - PCCP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 71a3db0367d5… | Dec 28, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO | ₱19,873,572.99 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26GA0124 | Jun 25, 2026 | AKLAN WEST RD (KALIBO-NABAS) - K0234 + (-375)- K0234 + 722, K0235 + 352 - K0235 + 667, K0236 + 912 - K0237 + 943, K0238 + 335 - K0238 + 461 | On-Going | ₱54.3M |
| 25GA0149 | Aug 20, 2025 | CONSTRUCTION OF SCHOOL BUILDING, TOLEDO NATIONAL HIGH SCHOOL, BARANGAY TOLEDO, NABAS, AKLAN | Completed | ₱9.9M |
| 25GA0150 | Aug 20, 2025 | CONSTRUCTION OF SCHOOL BUILDING, LASERNA INTEGRATED SCHOOL, BARANGAY LASERNA, NABAS, AKLAN | On-Going | ₱6.9M |
| 25GA0137 | Aug 14, 2025 | CONCRETING OF BRGY. RIZAL FMR, BRGY. RIZAL, NABAS, AKLAN | On-Going | ₱10.1M |
| 25GA0103 | May 23, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY TAGAROROC, NABAS, AKLAN | On-Going | ₱2.0M |
| 25GA0104 | May 23, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY PAWA, NABAS, AKLAN | On-Going | ₱1.6M |
| 25GA0105 | May 23, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY LIBERTAD, NABAS, AKLAN | On-Going | ₱1.7M |
| 25GA0108 | May 23, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY UNIDOS, NABAS, AKLAN | On-Going | ₱1.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.