Project 22GI0055
DPWH infrastructure contract
Contract ID:
22GI0055
Fingerprint:
18f5464c7bce83…fa9a716cae Verified
Status:
Terminated
Physical progress:
0%
Timeline:
Start Apr 1, 2022 (4 yrs 7 mo ago) · Target/actual end Dec 19, 2022
Description:
WIDENING OF BRIDGE - SIGANGAO PARALLEL BR. ALONG ILOILO EAST COAST-CAPIZ RD
Category:
Bridges
Implementing office:
DPWH Iloilo 4th DEO · Region VI
Contractor:
PATRILA BUILDERS, INC. · DPWH contractor code 26628
Contract amount:
₱0.00 (₱0)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 03d74d20c8dc… | Mar 22, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 4TH DEO | ₱31,351,883.09 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26GI0050 | Jun 5, 2026 | RECONSTRUCTION TO CONCRETE PAVEMENT - METRO ILOILO RADIAL RD (R4 BYPASS RD) - K0019 + 831 - K0020 + 064, K0020 + 168 - K0020 + 421 | Completed | ₱9.1M |
| 25GI0067 | Jun 4, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL PUBLIC MARKET) AT BARANGAY POBLACION ILAWOD, ZARRAGA, ILOILO | Completed | ₱4.9M |
| 25GI0046 | May 20, 2025 | CONSTRUCTION OF ROAD, BARANGAY JALAUD NORTE TO BALUD II, ZARRAGA, ILOILO | Completed | ₱4.9M |
| 25GI0043 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, ZARRAGA, ILOILO | Completed | ₱4.9M |
| 25GI0018 | Feb 18, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, ZARRAGA, ILOILO | Completed | ₱5.0M |
| 24GI0088 | Jul 9, 2024 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO EAST COAST-CAPIZ RD - K0284 + 777 - K0286 + 280 | Completed | ₱91.6M |
| 24GI0105 | Jul 9, 2024 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO EAST COAST-CAPIZ RD - K0286 + 280 - K0288 + 124 | Completed | ₱128.0M |
| 24GI0031 | May 24, 2024 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO EAST COAST-CAPIZ RD - K0283 + (-120) - K0284 + 100, K0284 + 467 - K0284 + 700 | Completed | ₱53.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.