Project 22HA0062
DPWH infrastructure contract
Contract ID:
22HA0062
Fingerprint:
161790d5ce450a…29cfa52d1e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 24, 2022 (4 yrs 7 mo ago) · Target/actual end May 28, 2022
Description:
CONSTRUCTION OF ROAD, CATIGBIAN, BOHOL
Category:
Roads
Implementing office:
DPWH Bohol 1st DEO · Region VII
Contractor:
JJF BUILDERS AND SUPPLY · DPWH contractor code 37015
Contract amount:
₱4,801,710.00 (₱4.8M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 312233897884… | Mar 22, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BOHOL 1ST ED | ₱4,801,710.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HA0087 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, AMBUAN, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0088 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, CAMBAILAN, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0089 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, KANG-IRAS, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0090 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, MAITUM, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0091 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, LIBORON, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0106 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, CAUSWAGAN NORTE, CATIGBIAN, BOHOL | Completed | ₱4.8M |
| 25HA0107 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, CANDUMAYAO, CATIGBIAN, BOHOL | Completed | ₱4.8M |
| 25HA0108 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BONGBONG, CATIGBIAN, BOHOL | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.