Completed
Physical progress:
100%
Timeline:
Start Feb 24, 2022 (4 yrs 8 mo ago) · Target/actual end Mar 10, 2023
Description:
CSSP : CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM -TRIP)-PILIPOG- GABI COASTAL ROAD (ROCK CAUSEWAY) LEADING TO HOTEL AND RESORT, CORDOVA, CEBU, PACKAGE II
Category:
Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Rehabilitation - PCCP
Implementing office:
DPWH Cebu 6th DEO · Region VII
Contractor:
WTG CONSTRUCTION AND DEVELOPMENT CORPORATION · DPWH contractor code 7494
As listed: WTG CONSTRUCTION & DEVELOPMENT CORPORATION
Contract amount:
₱96,500,000.00 (₱96.5M)
Funding source:
Regular Infra - Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Rehabilitation - PCCP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 56b8ad45c828… | Feb 10, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CEBU 6TH DEO | ₱96,231,312.50 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24HN0234 | Aug 7, 2025 | OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - MACTAN CIRCUMFERENTIAL RD-K0029 + 689 - K0030 + 221, CORDOVA, CEBU | Terminated | ₱0 |
| 25HN0137 | Jun 19, 2025 | CP: SPECIAL ROAD FUND-MVUC AS PER R.A. 11239 - INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG MCR - K0018+023 - K0020+151, K0031+765-K0034+775 (MODIFIED TO: K0011+(-634) - K0013+043, K0019+171-K0020+151, K0031+765 -K0034+775) | On-Going | ₱141.8M |
| 24HN0233 | Jun 3, 2025 | CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, CORDOVA, CEBU | Completed | ₱4.9M |
| 25HN0127 | Jun 3, 2025 | SSP: SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BUTUANON RIVER, BARANGAY CASUNTINGAN TO BARANGAY CABANCALAN (PHASE 7), MANDAUE CITY, CEBU | On-Going | ₱94.6M |
| 25HN0139 | Jun 3, 2025 | CP: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREET LIGHTS ALONG THE COASTAL ROAD OF BARANGAY PILIPOG AND BARANGAY SAN MIGUEL, CORDOBA, CEBU | Completed | ₱24.0M |
| 25H00082 | Apr 28, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF SEAWALL PROTECTION STRUCTURE (PHASE 2), CORDOVA, CEBU | On-Going | ₱97.0M |
| 25HN0073 | Apr 8, 2025 | CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, CORDOVA, CEBU | On-Going | ₱9.7M |
| 25HN0080 | Apr 8, 2025 | OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MACTAN CIRCUMFERENTIAL ROAD - K0026+000 - K0026+636, K0029+581 - K0030+228, CORDOVA, CEBU | Completed | ₱44.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.