Project 22IB0143
DPWH infrastructure contract
Contract ID:
22IB0143
Fingerprint:
053ac2b83c57a6…00fe24ee0a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 14, 2022 (3 yrs 11 mo ago) · Target/actual end Mar 8, 2024
Description:
CONSTRUCTION OF ROAD FROM BRGY. CAMADA TO BRGY. PINANAG-AN, BORONGAN CITY, EASTERN SAMAR
Category:
GAA 2022 CSSP
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
J.A. DEVELOPERS AND ENGINEERS · DPWH contractor code 43714
Contract amount:
₱44,099,954.23 (₱44.1M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 05eaf9119a9d… | Oct 27, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO | ₱43,045,598.63 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26IB0098 | Aug 17, 2026 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/ FACILITIES REHABILITATION OF ROAD, BARANGAY CANJAWAY, BORONGAN CITY, EASTERN S | On-Going | ₱9.6M |
| 24IB0142 | Jan 22, 2026 | CONSTRUCTION OF POTABLE WATER SYSTEM LEVEL III, FILTRATION AND PURIFICATION SYSTEM, EASTERN SAMAR STATE UNIVERSITY - MAIN CAMPUS, BORONGAN CITY, EASTERN SAMAR | On-Going | ₱84.6M |
| 25IB0187 | Jan 22, 2026 | CONSTRUCTION OF CLASSROOMS, LAWAAN CENTRAL ELEMENTARY SCHOOL, LAWAAN, EASTERN SAMAR | On-Going | ₱8.8M |
| 25IB0191 | Jan 22, 2026 | CONSTRUCTION OF CLASSROOMS, GUINMAAYOHAN ELEMENTARY SCHOOL, BALANGIGA, EASTERN SAMAR | On-Going | ₱8.7M |
| 25IB0195 | Jan 22, 2026 | CONSTRUCTION OF ROAD PUROK 1 KAWAYAN, BARANGAY DAPDAP TO RAWISWIS BEACH, DOLORES, EASTERN SAMAR | On-Going | ₱9.8M |
| 25IB0198 | Jan 22, 2026 | REPAIR/ REHABILITATION OF CLASSROOMS, GIGOSO ELEMENTARY SCHOOL, GIPORLOS, EASTERN SAMAR | On-Going | ₱2.6M |
| 25IB0199 | Jan 22, 2026 | REPAIR/ REHABILITATION OF CLASSROOMS, SOUTHERN SAMAR NATIONAL COMPREHENSIVE HIGH SCHOOL, BALANGIGA, EASTERN SAMAR | On-Going | ₱10.8M |
| 25IB0205 | Jan 22, 2026 | CONSTRUCTION OF 2 CLASSROOM SCHOOL BUILDING W/ SOLAR PV, RAINWATER COLLECTOR WATER SYSTEM & PROVISION OF FURNITURES, CATI-AN ELEMENTARY SCHOOL, CITY OF BORONGAN, EASTERN SAMAR | On-Going | ₱17.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.