Project 22IK0031
DPWH infrastructure contract
Contract ID:
22IK0031
Fingerprint:
a64487cfb28d67…2a01aecfff Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 4, 2022 (4 yrs 8 mo ago) · Target/actual end Sep 12, 2022
Description:
CONSTRUCTION OF ROAD, HINANGUTDAN, ST. RITA TO SAN ROQUE, VILLAREAL (PHASE IV), HINANGUTDAN, STA. RITA TO SAN ROQUE, VILLAREAL, SAMAR, STA. 7+200 - STA. 10+280
Category:
Roads
Implementing office:
DPWH Samar 2nd DEO · Region VIII
Contractor:
SOLID M CONSTRUCTION · DPWH contractor code 33991
Contract amount:
₱86,846,889.64 (₱86.8M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24IK0039 | Feb 23, 2024 | CONST. OF MULTI- PURPOSE BUILDING, VILLAREAL NATIONAL HIGH SCHOOL, BRGY. TAYUD, VILLAREAL, SAMAR | On-Going | ₱5.9M |
| 23IK0106 | Oct 31, 2023 | CONSTRUCTION OF MULTI- PURPOSE BUILDING (EVACUATION CENTER), VILLAREAL, SAMAR | Completed | ₱39.2M |
| 23IK0060 | May 2, 2023 | CONSTRUCTION OF ROAD LEADING TO BANQUIL PORT, VILLAREAL, SAMAR, STA. 0+927.00 - STA. 1+260.50 | Completed | ₱9.8M |
| 22IK0072 | Mar 24, 2022 | CONSTRUCTION OF ROAD, CANMUCAT - TOMABE - INASUDLAN, VILLAREAL STA. 0+660 - STA. 2+500, BRGY. CANMUCAT - TOMABE - INASUDLAN, VILLAREAL, SAMAR | Completed | ₱67.5M |
| 22IK0075 | Mar 22, 2022 | CONST. OF ROAD, CANMUCAT-TOMABE-INASUDLAN, VILLAREAL, STA. 2+500-STA. 2+600, BRGY. CANMUCAT-TOMABE-INASUDLAN, VILLAREAL, SAMAR | Completed | ₱14.8M |
| 22IK0065 | Mar 17, 2022 | BASIC INFRASTRUCTURE PROGRAM (BIP)-CONST. OF SAN ANDRES - INARUMBACAN - LAWAAN - PLARIDEL - POLANGI ROAD, VILLAREAL, SAMAR, STA. 0+000 - STA. 0+700, VILLAREAL, SAMAR | Completed | ₱24.7M |
| 21IK0044 | Nov 12, 2021 | CONSTRUCTION/REHAB. OF MULTI-PURPOSE BUILDING, BRGY. PACAO, VILLAREAL, SAMAR | On-Going | ₱4.8M |
| 21IK0055 | Sep 21, 2021 | CONSTRUCTION/COMPLETION OF MODIFIED DESIGN WITH PARAPET 2 STOREY, 4 CL SCHOOL BLDG., CONANT E/S, VILLAREAL, SAMAR | Completed | ₱13.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.