Project 22KE0055
DPWH infrastructure contract
Contract ID:
22KE0055
Fingerprint:
1b81f97f61330d…119d9a67f5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 20, 2022 (4 yrs 6 mo ago) · Target/actual end Oct 2, 2023
Description:
CONSTRUCTION OF ROAD,POBLACION,MAMBAJAO,CAMIGUIN
Category:
Roads
Implementing office:
DPWH Camiguin DEO · Region X
Contractor:
FNTC CONSTRUCTION · DPWH contractor code 50251
Contract amount:
₱11,632,882.15 (₱11.6M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 45d71c813c2d… | Mar 24, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMIGUIN DEO | ₱11,632,882.15 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26KE0004 | Jul 30, 2026 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS - CAMIGUIN CIRCUMFERENTIAL ROAD - K0005 + 934 - K0006 + 034 | On-Going | ₱8.7M |
| 25KE0061 | Feb 10, 2026 | REPAIR/REHABILITATION OF 2 CLASSROOMS, BINUNSARAN ELEMENTARY SCHOOL, MAMBAJAO, CAMIGUIN | On-Going | ₱1.3M |
| 25KE0065 | Feb 10, 2026 | RESTORATION AND CONSERVATION OF GABALDON AND OTHER HERITAGE SCHOOL BUILDING, KUGUITA INTEGRATED SCHOOL, MAMBAJAO, CAMIGUIN | On-Going | ₱4.5M |
| 25KE0060 | Nov 6, 2025 | CONSTRUCTION OF SCHOOL BUILDING, MAGTING ELEMENTARY SCHOOL, MAGTING, MAMBAJAO, CAMIGUIN | On-Going | ₱12.7M |
| 25KE0038 | Sep 29, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT, BOARDWALK AND LANDSCAPING BARANGAY POBLACION, MAMBAJAO, CAMIGUIN | On-Going | ₱49.2M |
| 25KE0039 | Sep 29, 2025 | CONSTRUCTION OF BOARDWALK WITH VIEW DECK (OLD WHARF), PHASE II, MUNICIPAL PLAZA, BARANGAY POBLACION, MAMBAJAO, CAMIGUIN | On-Going | ₱49.2M |
| 25KE0017 | Jun 12, 2025 | CONSTRUCTION OF ROADS, BARANGAYS AGOHO, BUG-ONG AND MAGTING, MAMBAJAO, CAMIGUIN | On-Going | ₱9.6M |
| 25KE0041 | Jun 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) SITIO BINUNSARAN, MAMBAJAO, CAMIGUIN | On-Going | ₱9.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.