Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 22KJ0003

DPWH infrastructure contract
Contract ID:
22KJ0003
Fingerprint:
2b4a63e155fb15…cbd0ab1e98 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 18, 2022 (4 yrs 8 mo ago) · Target/actual end Jul 5, 2022
Description:
PREVENTIVE MAINTENANCE-TERTIARY ROADS OZAMIZ BYPASS ROAD K1700+(-563)-K1701+397, OZAMIZ BYPASS ROAD K1700+(-563)-K1701+397
Category:
Roads
Implementing office:
Contractor:
MINDANAO ROCK · DPWH contractor code 23479
Contract amount:
₱45,976,846.00 (₱46.0M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
5f367c91a459…Feb 8, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MIS. OCC. SUB-DEO₱45,976,846.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25KJ0117Oct 16, 2025ROAD WIDENING - PRIMARY ROADS OZAMIZ - PAGADIAN RD., K1669+287 - K1669+516.5, K1669+545.5 - K1670+070, K1691+324 - K1692+124.5, K1692+145.5 - K1692+566.982, K1692+678.941- K1692+789On-Going₱82.1M
25KJ0039Jul 21, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, BRGY. MANAKA - GALA, OZAMIZ CITY, MISAMIS OCCIDENTALCompleted₱29.1M
25KJ0041Jul 21, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, (KINUMAN SUR - GALA SECTION), OZAMIZ CITY, MISAMIS OCCIDENTALCompleted₱48.5M
25KJ0042Jul 21, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, (KINUMAN NORTE - GALA SECTION), OZAMIZ CITY, MISAMIS OCCIDENTALCompleted₱29.1M
25KJ0043Jul 21, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, PUROK 5 - PUROK 6, BRGY. DIMALUNA SECTION, OZAMIZ CITYCompleted₱38.2M
25KJ0044Jul 21, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD,P3-P4 TABID SECTION, OZAMIZ CITY, MISAMIS OCCIDENTALCompleted₱29.1M
25KJ0045Jul 21, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, (P2-TABID SECTION, OZAMIZ CITY, MISAMIS OCCIDENTALCompleted₱29.1M
25KJ0093Jul 21, 2025RAINWATER COLLECTOR SYSTEM, MISAMIS OCCIDENTAL 2ND DEOCompleted₱2.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.