Project 22KJ0084
DPWH infrastructure contract
Contract ID:
22KJ0084
Fingerprint:
8a46dff080c05c…b101d9bb93 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 23, 2022 (4 yrs 5 mo ago) · Target/actual end May 29, 2023
Description:
REHABILITATION OF OZAMIZ CITY CIRCUMFERENTIAL ROAD, (LAM-AN TO CATADMAN SECTION) WITH STREETLIGHTS, OZAMIZ CITY, MISAMIS OCCIDENTAL
Category:
Roads
Implementing office:
DPWH Misamis Occidental 2nd DEO · Region X
Contractor:
MINDANAO ROCK · DPWH contractor code 23479
Contract amount:
₱47,530,000.00 (₱47.5M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d471ef60025d… | May 13, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MIS. OCC. SUB-DEO | ₱47,530,000.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25KJ0117 | Oct 16, 2025 | ROAD WIDENING - PRIMARY ROADS OZAMIZ - PAGADIAN RD., K1669+287 - K1669+516.5, K1669+545.5 - K1670+070, K1691+324 - K1692+124.5, K1692+145.5 - K1692+566.982, K1692+678.941- K1692+789 | On-Going | ₱82.1M |
| 25KJ0039 | Jul 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, BRGY. MANAKA - GALA, OZAMIZ CITY, MISAMIS OCCIDENTAL | Completed | ₱29.1M |
| 25KJ0041 | Jul 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, (KINUMAN SUR - GALA SECTION), OZAMIZ CITY, MISAMIS OCCIDENTAL | Completed | ₱48.5M |
| 25KJ0042 | Jul 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, (KINUMAN NORTE - GALA SECTION), OZAMIZ CITY, MISAMIS OCCIDENTAL | Completed | ₱29.1M |
| 25KJ0043 | Jul 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, PUROK 5 - PUROK 6, BRGY. DIMALUNA SECTION, OZAMIZ CITY | Completed | ₱38.2M |
| 25KJ0044 | Jul 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD,P3-P4 TABID SECTION, OZAMIZ CITY, MISAMIS OCCIDENTAL | Completed | ₱29.1M |
| 25KJ0045 | Jul 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, (P2-TABID SECTION, OZAMIZ CITY, MISAMIS OCCIDENTAL | Completed | ₱29.1M |
| 25KJ0093 | Jul 21, 2025 | RAINWATER COLLECTOR SYSTEM, MISAMIS OCCIDENTAL 2ND DEO | Completed | ₱2.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.