Completed
Physical progress:
100%
Timeline:
Start Feb 28, 2022 (4 yrs 8 mo ago) · Target/actual end Oct 23, 2022
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT GITAGUM RIVER, GITAGUM MISAMIS ORIENTAL
Category:
Flood Control and Drainage
Implementing office:
DPWH Misamis Oriental 2nd DEO · Region X
Contractor:
ROAD EDGE TRADING AND DEVELOPMENT SERVICES · DPWH contractor code 33140
As listed: ROAD EDGE TRADING & DEVELOPMENT SERVICES
Contract amount:
₱48,250,000.00 (₱48.3M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 469794692dab… | Feb 18, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MISAMIS ORIENTAL 2 | ₱47,384,089.92 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26KL0106 | Aug 17, 2026 | INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG BUTUAN CITY - CAGAYAN DE ORO CITY - ILIGAN CITY RD - K1472+000 - K1473+373 | On-Going | ₱23.6M |
| 26KL0061 | Jul 3, 2026 | INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING, PAVEMENT MARKINGS) ALONG BUTUAN CITY - CAGAYAN DE ORO CITY - ILIGAN CITY RD - K1473 + 399 - K1474 + 424.39 | On-Going | ₱24.0M |
| 25K00415 | Jun 9, 2025 | CONSTRUCTION OF ROAD AT LAGUINDINGAN-ILIGAN CITY ALTERNATE ROAD, PACKAGE 1, MISAMIS ORIENTAL | On-Going | ₱293.4M |
| 25KL0003 | May 22, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY POBLACION, GITAGUM MISAMIS ORIENTAL | On-Going | ₱4.9M |
| 25KL0013 | Mar 21, 2025 | CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY C.P. GARCIA, GITAGUM, MISAMIS ORIENTAL | On-Going | ₱4.9M |
| 25KL0047 | Mar 21, 2025 | CONSTRUCTION OF MULTIPURPOSE BUILDING (MATANGAD ES), BARANGAY MATANGAD, GITAGUM, MISAMIS ORIENTAL | On-Going | ₱9.8M |
| 25KL0007 | Feb 4, 2025 | CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY AROMAHON, LAGUINDINGAN, MISAMIS ORIENTAL | Completed | ₱4.9M |
| 25KL0057 | Feb 4, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BURNAY ELEM. SCHOOL), BARANGAY BURNAY, GITAGUM, MISAMIS ORIENTAL | On-Going | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.