Project 22LA0043

DPWH infrastructure contract
Contract ID:
22LA0043
Fingerprint:
0ec755287aacd5…49dcfa9b22 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 15, 2022 (4 yrs 9 mo ago) · Target/actual end Nov 8, 2022
Description:
CONSTRUCTION OF REVETMENT ALONG LINDA CREEK, STA. 3+000 - STA. 3+430 (RS), STA. 1+500 - STA. 2+500 (LS), STA. 2+000 - STA. 2+520 (RS), BRGY. LINDA, NABUNTURAN, DAVAO DE ORO
Category:
Flood Control and Drainage
Implementing office:
Contractor:
Contract amount:
₱48,999,953.58 (₱49.0M)
Funding source:
Regular Infra - GAA 2022 OO-2
Budget year:
2022

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26LC0037Jul 9, 2026NABUNTURAN-LAAK ROAD, BARANGAY SANTA FE (STA.6+429.650 + STA. 6+505.65), NEW CORELLA, DAVAO DEL NORTEOn-Going₱94.4M
25LA0068Sep 3, 2025CONSTRUCTION (COMPLETION) OF ADMINISTRATIVE BUILDING, DAVAO DE ORO 1ST DEO, NABUNTURAN, DAVAO DE OROOn-Going₱19.6M
25LA0079Sep 3, 2025CONSTRUCTION OF ROAD, BARANGAY MAINIT-PANARAON, MACO, DAVAO DE OROOn-Going₱48.0M
25LA0098Sep 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DAUIS, NABUNTURAN, DAVAO DE OROOn-Going₱5.9M
25LA0077Jul 28, 2025CONSTRUCTION OF (COMPLETION) MULTI-PURPOSE BUILDING, BARANGAY KAO ELEMENTARY SCHOOL, NABUNTURAN, DAVAO DE OROOn-Going₱2.9M
25LA0088Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, HALL OF JUSTICE, BARANGAY CABIDIANAN, NABUNTURAN, DAVAO DE OROOn-Going₱34.6M
25LA0091Jul 28, 2025CONSTRUCTION OF (COMPLETION) MULTI-PURPOSE BUILDING, BARANGAY LIBASAN ELEMENTARY SCHOOL, NABUNTURAN, DAVAO DE OROOn-Going₱3.9M
25LA0078Jul 8, 2025CONSTRUCTION OF (COMPLETION) MULTI-PURPOSE BUILDING, BARANGAY KAO NATIONAL HIGH SCHOOL, NABUNTURAN, DAVAO DE OROCompleted₱2.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.