Project 22LG0035
DPWH infrastructure contract
Contract ID:
22LG0035
Fingerprint:
ccbf98d635a487…f3c7c56e6e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 28, 2022 (4 yrs 8 mo ago) · Target/actual end May 27, 2022
Description:
CONSTRUCTION OF CONCRETE ROAD - LUPON COASTAL ROAD FROM PUROK SAN ROQUE, BRGY. POBLACION TO PUROK BUNDAS, BRGY. BAGUMBAYAN LEADING TO DIVING SITE, WENCESLAO RESORT, & ARIGID AI BEACH RESORT, BRGY. BAGUMBAYAN, LUPON, DAVAO ORIENTAL
Category:
Roads
Implementing office:
DPWH Davao Oriental 2nd DEO · Region XI
Contractor:
AGONG BUILDERS AND CONSTRUCTION SUPPLY, INC. · DPWH contractor code 40494
Contract amount:
₱9,800,000.00 (₱9.8M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| c5724d96ce63… | Feb 11, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - DAVAO ORIENTAL 2ND | ₱9,779,914.93 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25LG0051 | Aug 21, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY- PRES. DIOSDADO P. MACAPAGAL NAT'L HI-WAY 1748+500-K1749+184, K1749 + 506 - K1750 +142 | On-Going | ₱95.5M |
| 25LG0072 | Aug 21, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG LOGDECK RIVER, LUPON, DAVAO ORIENTAL | On-Going | ₱98.0M |
| 25LG0073 | Jul 7, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PANGYAN UPPER SUMLOG RIVER, LUPON, DAVAO ORIENTAL | On-Going | ₱97.0M |
| 25LG0033 | May 26, 2025 | PREVENTIVE MAINTENANCE OF ROAD:ASPHALT OVERLAY-PRES. DIOSDADO P. MACAPAGAL NATL HI-WAY-K1745+281-K1746+299,K1748+122-K1748+500 | Completed | ₱96.5M |
| 25LG0010 | Mar 27, 2025 | CONSTRUCTION OF LONGCALOB BRIDGE APPROACHES , NEW VISAYAS- SAN ISIDRO-LONGCALOB ROAD, LUPON, DAVAO ORIENTAL | On-Going | ₱28.8M |
| 25LG0025 | Mar 27, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, DONCAMAR, LUPON, DAVAO ORIENTAL | On-Going | ₱93.6M |
| 25LG0062 | Mar 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, PACKAGE 2, LUPON, DAVAO ORIENTAL | On-Going | ₱5.4M |
| 25LG0064 | Mar 27, 2025 | CONSTRUCTION OF MULTI -PURPOSE BUILDING, PACKAGE 3, LUPON, DAVAO ORIENTAL | On-Going | ₱8.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.