Project 22MG0024
DPWH infrastructure contract
Contract ID:
22MG0024
Fingerprint:
69daaec314c975…7ef84c5f1f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 24, 2022 (4 yrs 7 mo ago) · Target/actual end Aug 26, 2022
Description:
CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG SURALLAH-LAKE SEBU-MAITUM RD-(S00838MN) (KENUBING SECTION) K1806+025-K1806+820
Category:
Roads
Implementing office:
DPWH South Cotabato 2nd DEO · Region XII
Contractor:
C.A. BETALAC CONSTRUCTION & GEN. MDSE INC. · DPWH contractor code 28222
As listed: C.A. BETALAC CONSTRUCTION & GEN. MDSE., INC. (FOR: C.A. BETALAC CONSTRUCTION & GEN. MDSE.)
Contract amount:
₱48,999,999.12 (₱49.0M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| b3b278f65c0a… | Mar 22, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTH COTABATO 1ST | ₱48,749,742.17 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26MG0017 | Jun 17, 2026 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE-SURALLAH-LAKE SEBU-MAITUM RD-K1745+300-K1745+453 | On-Going | ₱35.2M |
| 26MG0010 | Jun 11, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1757+291-K1757+760 | On-Going | ₱9.1M |
| 26MG0012 | Jun 11, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1759+000-K1761+020 | Completed | ₱21.9M |
| 26MG0011 | Jun 4, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1755+815-K1757+291 | Completed | ₱19.7M |
| 25MG0112 | Aug 20, 2025 | CONSTRUCTION OF SCHOOL BUILDING, UBO ELEMENTARY SCHOOL-LAMFENEK EXTENSION, BARANGAY LAMFUGON, LAKE SEBU, SOUTH COTABATO | Completed | ₱5.0M |
| 25M00052 | Aug 5, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SURALLAH-LAKE SEBU-MAITUM RD - K1799+460 - K1799+580, K1827+970 - K1828+022, LAKE SEBU, SOUTH COTABATO | On-Going | ₱93.6M |
| 25MG0110 | Jun 27, 2025 | CLUSTER I-A.CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS), KIANTAY ELEMENTARY SCHOOL, SITIO KIANTAY, BRGY. UPPER SEPAKA, SURALLAH, SOUTH COTABATO B.CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS), NEW TUPI IS, SITIO NEW TUPI, BRGY. NED, LAKE SEBU, S | Completed | ₱2.6M |
| 25MG0016 | Apr 11, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1755+262-K1755+815, SOUTH COTABATO | Completed | ₱13.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.