DPWH infrastructure contract
Contract ID:
22N00109
Fingerprint:
bbe28c4e9c3715…b9259f7870 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 18, 2022 (4 yrs 7 mo ago) · Target/actual end Nov 12, 2022
Description:
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (DOWNSTREAM RIGHT SIDE OF MAHAYAHAY BRIDGE), BRGY. MAHAYAHAY, STA. 0+000.00- STA. 0+500.00, KITCHARAO, AGUSAN DEL NORTE
Category:
Flood Control and Drainage
Implementing office:
DPWH Region XIII · Region XIII
Contractor:
C'ZARLES CONSTRUCTION & SUPPLY · DPWH contractor code 23426
Contract amount:
₱115,799,987.57 (₱115.8M)
Funding source:
Regular Infra - GAA 2022 OO-2
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
3537ac628c67…Feb 28, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XIII (CARAG₱106,597,010.04

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26NA0031Jul 9, 2026CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BRGY. HINIMBANGAN, KITCHARAO, AGUSAN DEL NORTE (9.441949, 125.617128)On-Going₱6.9M
25NA0038Mar 24, 2025CONCRETING OF BRGY. SAN ISIDRO-BARAAS FMR, SITIO BARAAS, BRGY. SAN ISIDRO, KITCHARAO, AGUSAN DEL NORTECompleted₱14.9M
25NA0010Feb 13, 2025CONSTRUCTION OF WATER SUPPLY SYSTEM - LEVEL II, NEW EVACUATION CENTER, PUROK 5, SERINGAN, BARANGAY POBLACION, KITCHARAO, AGUSAN DEL NORTECompleted₱4.9M
24N00025Oct 17, 2024DAANG MAHARLIKA (SURIGAO - AGUSAN SECT)- K1176+655 - K1176+750On-Going₱5.4M
24N00187Sep 20, 2024CONSTRUCTION OF JALIOBONG-SAN ISIDRO RIVER CONTROL PROJECT, KITCHARAO, AGUSAN DEL NORTECompleted₱241.2M
24N00027Jul 19, 2024DAANG MAHARLIKA (SURIGAO-AGUSAN SECT)- K1176+750- K1176+960Completed₱10.8M
24NA0031Apr 23, 2024CONSTRUCTION OF MAMKAS FLOOD CONTROL PROJECT, PACKAGE 2, AGUSAN DEL NORTECompleted₱24.4M
24N00026Apr 11, 2024DAANG MAHARLIKA (SURIGAO-AGUSAN SECT)- K1169+720 - K1170+000Completed₱11.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.