Project 22NF0107
DPWH infrastructure contract
Contract ID:
22NF0107
Fingerprint:
564894737646f1…7525758789 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 5, 2022 (4 yrs 4 mo ago) · Target/actual end Oct 2, 2022
Description:
COMPLETION OF MULTI-PURPOSE BUILDING, BRGY. 3, DAPA, SURIGAO DEL NORTE
Category:
Buildings and Facilities
Implementing office:
DPWH Surigao del Norte 1st DEO · Region XIII
Contractor:
RADIAN CONSTRUCTION AND SUPPLY · DPWH contractor code 43184
Contract amount:
₱2,968,000.00 (₱3.0M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| c57ad2a21f7d… | Jun 27, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SURIGAO DEL NORTE | ₱2,968,000.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26NF0003 | Jul 1, 2026 | NETWORK DEVELOPMENT PROGRAM ROAD WIDENING - SECONDARY ROADS DAPA - GEN LUNA RD - K0002+539 - K0004+000 | On-Going | ₱42.6M |
| 26NF0029 | May 29, 2026 | REHABILITATION OF MULTI-PURPOSE BUILDING (LGU HOTEL), BARANGAY 6, DAPA, SURIGAO DEL NORTE | On-Going | ₱4.9M |
| 25NF0072 | Jul 18, 2025 | CONSTRUCTION OF UNION-BUTONG-CONSUELO ROAD, DAPA, SURIGAO DEL NORTE | On-Going | ₱93.6M |
| 25NF0087 | Jul 18, 2025 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG NRJ DON PAULINO-BINGAG-OSMENA PHASE 2, DAPA, SURIGAO DEL NORTE | Completed | ₱144.6M |
| 25NF0088 | Jul 18, 2025 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG NRJ DON PAULINO-BINGAG-OSMENA PHASE 3, DAPA, SURIGAO DEL NORTE | Completed | ₱96.4M |
| 25NF0023 | Apr 3, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG DAPA TO SITIO LOBO - BARANGAY 12 PHASE 1, DAPA, SURIGAO DEL NORTE | Completed | ₱115.7M |
| 25NF0024 | Apr 3, 2025 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG NRJ DON PAULINO - BINGAG - OSMENA PHASE I, DAPA, SURIGAO DEL NORTE | Completed | ₱72.3M |
| 25NF0013 | Mar 28, 2025 | PREVENTIVE MAINTENANCE - TERTIARY ROADS - DAPA - UNION - GEN. LUNA ROAD - K0001+(-468) - K0002+194 | Completed | ₱67.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.