Project 22OB0082
DPWH infrastructure contract
Contract ID:
22OB0082
Fingerprint:
aee280d57b79b2…1605cb97b6 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 21, 2022 (4 yrs 7 mo ago) · Target/actual end Oct 18, 2022
Description:
REHABILITATION OF MULTI-PURPOSE BUILDING AT BARANGAY CANIOGAN, PASIG CITY
Category:
Buildings and Facilities
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
PRUDENT DIAMOND SQUARE CONSTRUCTION CO. · DPWH contractor code 31726
Contract amount:
₱24,683,296.15 (₱24.7M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| cb5371f98a19… | Mar 14, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 1ST E | ₱24,683,296.15 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26OB0090 | Jun 22, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - PASIG BLVD C5 FLYOVER (B01876LZ) ALONG C-5 ROAD | On-Going | ₱74.3M |
| 26OB0088 | May 21, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - C5/ORTIGAS FLYOVER (B03319LZ) ALONG C5- ORTIGAS FLYOVER, PHASE II | On-Going | ₱97.8M |
| 26OB0089 | May 21, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - ORTIGAS BR. (B01868LZ) ALONG MANILA EAST RD (ROSARIO-CAINTA RD) | On-Going | ₱89.9M |
| 26OB0091 | May 12, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - C5/ORTIGAS FLYOVER (B03318LZ) ALONG C5- ORTIGAS FLYOVER, PHASE II | On-Going | ₱25.4M |
| 26OB0092 | May 12, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - DAAN PASIG BR. (B01874LZ) ALONG AMANG RODRIGUEZ RD | On-Going | ₱23.8M |
| 25OB0461 | Jun 20, 2025 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM IN PUBLIC FACILITIES IN METRO MANILA 1ST DISTRICT ENGINEERING OFFICE | Completed | ₱2.6M |
| 25OG0038 | May 23, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 4, BARANGAY BAGUMBAYAN, QUEZON CITY | On-Going | ₱48.0M |
| 25OG0039 | May 23, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 5, BARANGAY BAGUMBAYAN, QUEZON CITY | On-Going | ₱48.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.