Project 22OB0195
DPWH infrastructure contract
Contract ID:
22OB0195
Fingerprint:
9b0d56553f5b86…827e7121ba Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 16, 2022 (4 yrs 8 mo ago) · Target/actual end May 16, 2022
Description:
PREVENTIVE MAINTENANCE ALONG MARCOS HIGHWAY WESTBOUND, K0017 + (-009 ) - K0014 + 606, PASIG-MARIKINA CITY
Category:
Roads
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
PHILIPPINE CHEMSTEEL INDUSTRIES, INC. · DPWH contractor code 16965
Contract amount:
₱91,645,889.14 (₱91.6M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| e3a4c25c6a88… | Feb 9, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 1ST E | ₱91,645,889.14 |
| a7f473d4ee88… | Feb 9, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 1ST E | ₱91,645,889.14 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OB0459 | May 22, 2025 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - MARIKINA BR. (B01866LZ) ALONG A BONIFACIO AVE | On-Going | ₱144.9M |
| 25OB0262 | May 20, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, NANGKA RIVER,MARIKINA CITY | Completed | ₱47.8M |
| 25OB0263 | May 20, 2025 | REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG NANGKA RIVER, MARIKINA CITY | Completed | ₱38.1M |
| 25OB0285 | May 20, 2025 | INSTALLATION OF ROAD SAFETY DEVICES ALONG ORDONEZ STREET, SECOND DISTRICT, MARIKINA CITY | On-Going | ₱38.0M |
| 25OB0287 | May 20, 2025 | INSTALLATION OF ROAD SAFETY DEVICES ALONG F. MANALO STREET INCLUDING LATERALS, BARANGAY NANGKA, MARIKINA CITY | Completed | ₱9.5M |
| 25OB0289 | May 20, 2025 | INSTALLATION OF M. SEVILLA ROAD SAFETY DEVICES INCLUDING LATERALS, BARANGAY PARANG, MARIKINA CITY | Completed | ₱9.3M |
| 25OB0290 | May 20, 2025 | INSTALLATION OF SHOE AVENUE, AMANG RODRIGUEZ, ROAD SAFETY DEVICES, BARANGAY CONCEPCION UNO, MARIKINA CITY | Completed | ₱9.5M |
| 25OB0294 | May 20, 2025 | INSTALLATION OF ORO VISTA SUBDIVISION ROAD SAFETY DEVICES, BARANGAY CONCEPCION UNO, MARIKINA CITY | On-Going | ₱9.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.