Project 22OB0327
DPWH infrastructure contract
Contract ID:
22OB0327
Fingerprint:
8ab39d7a68c64e…91653e70bd Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 15, 2022 (4 yrs 8 mo ago) · Target/actual end Apr 13, 2022
Description:
REHABILITATION OF ROAD NETWORK, BARANGAY CONCEPCION DOS, MARIKINA CITY
Category:
Roads
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
M3 KONSTRACT CORPORATION · DPWH contractor code 20201
As listed: M3 KONSTRACT CORPORATION (FORMERLY:MARGARITA CONSTRUCTION)
Contract amount:
₱7,442,195.00 (₱7.4M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| db229a596a1f… | Mar 8, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 1ST E | ₱7,442,195.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DN0104 | Jun 16, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - CORAZON C. AQUINO AVE. - K0029+580 - K0030+197 ANTIPOLO CITY (SECOND DISTRICT) | On-Going | ₱18.7M |
| 25DN0105 | Jun 16, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - MARIKINA - INFANTA RD - K0035+908.00 - K0036+000.00 ANTIPOLO CITY (SECOND DISTRICT) | Completed | ₱4.8M |
| 25DN0113 | Jun 16, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - MARIKINA - INFANTA RD - K0035+000.00 - K0035+738.00 ANTIPOLO CITY (SECOND DISTRICT) | Completed | ₱30.9M |
| 25DO0077 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD BARANGAY SILANGAN TO BARANGAY | On-Going | ₱47.2M |
| 25DN0096 | May 29, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - CORAZON C. AQUINO AVE. - K0029+400 - K0029+500, ANTIPOLO CITY (SECOND DISTRICT) | Completed | ₱5.1M |
| 25DN0100 | May 29, 2025 | IMPROVEMENT OF ROAD, OLALIA ROAD, PHASE II, BARANGAY STA CRUZ AND BARANGAY DELA PAZ, ANTIPOLO CITY (FIRST DISTRICT) | On-Going | ₱9.6M |
| 25DN0102 | May 29, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, PUROK 5, ZONE 8, BARANGAY CUPANG, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | On-Going | ₱5.0M |
| 25DN0103 | May 29, 2025 | CONSTRUCTION OF SLOPE PROTECTION, BO. CUPANG/ LITTLE TONDO, BARANGAY CUPANG, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | On-Going | ₱5.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.