Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 22OD0264

DPWH infrastructure contract
Contract ID:
22OD0264
Fingerprint:
0efbce8a9dea55…95191fbd40 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 6, 2022 (4 yrs 5 mo ago) · Target/actual end Oct 28, 2022
Description:
RETROFITTING/ STRENGTHENING OF PUBLIC BUILDINGS IN PREPARATION FOR THE 'BIG ONE' BAESA HIGH SCHOOL, BRGY. 168, CALOOCAN CITY
Category:
GAA 2022 LP
Implementing office:
DPWH Metro Manila 3rd DEO · National Capital Region
Contractor:
D. T. RECIO, INCORPORATED · DPWH contractor code 44927
As listed: D.T. RECIO INCORPORATED
Contract amount:
₱10,956,272.29 (₱11.0M)
Funding source:
Regular Infra - GAA 2022 LP
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1330fd7dfe20…Jun 2, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (METRO MANILA 3RD ED₱10,956,272.29

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OD0370Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, NORTH OLYMPUS, BARANGAY 172, CALOOCAN CITYOn-Going₱9.2M
25OD0371Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 156, CALOOCAN CITYOn-Going₱10.5M
25OD0373Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), CELINA HOMES, BARANGAY 168, CALOOCAN CITYOn-Going₱4.8M
25OD0374Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE 2, BARANGAY 171, CALOOCAN CITYCompleted₱4.8M
25OD0375Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BARANGAY 176, CALOOCAN CITY (PHASE 3)On-Going₱23.9M
25OD0376Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 180, CALOOCAN CITYOn-Going₱28.6M
25OD0368Jul 21, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 153, CALOOCAN CITYOn-Going₱28.7M
25OD0360Jul 9, 2025CONSTRUCTION (COMPLETION) PUP NORTH CALOOCAN CITY CAMPUS ACADEMIC BUILDING INCLUDING GROUND IMPROVEMENT (PHASE 6), BRGY. 168, CALOOCAN CITYOn-Going₱139.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.