Project 22PF0054
DPWH infrastructure contract
Contract ID:
22PF0054
Fingerprint:
f041eaa513e602…bf32e9e863 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 1, 2022 (4 yrs 5 mo ago) · Target/actual end Mar 27, 2023
Description:
REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS, GOV. BADO DANGWA NATIONAL ROAD: K0328+236-K0328+246, K0328+352-K0328+371, K0332+188-K0332+198, K0339+305-K0339+334, K0340+800-KO341+000, K0341+900-K0342+000,
Category:
Roads
Implementing office:
DPWH Benguet 2nd DEO · Cordillera Administrative Region
Contractor:
HIGH PLAIN CONSTRUCTION (47818) / R.S. SEPIAN CONSTRUCTION & TRUCKING · DPWH contractor code 20519
Contract amount:
₱64,655,000.00 (₱64.7M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25PF0079 | Aug 14, 2026 | REHABILITATION OF DAMAGED SLOPE PROTECTION STRUCTURES AND OTHER CONCRETE STRUCTURES CAUSED BY SOUTHWEST MONSOON AND TROPICAL CYCLONE MIRASOL, NANDO, AND OPONG, GOV. BADO DANGWA NATIONAL ROAD K0329+810-K0329+830, PALINA, KIBUNGAN, BENGUET | On-Going | ₱1.4M |
| 25PF0009 | Apr 8, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS: GOV. BADO DANGWA NATIONAL RD - K0325+110 - K0325+125, K0329+830-K0330+100, K0334+080-K0334+135, K0334+942 - K0335+000, K0336+068 - K0336+110, K0336+351 - K0 | On-Going | ₱35.5M |
| 25PF0023 | Apr 8, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS: GOV. BADO DANGWA NATIONAL RD - K0346+330 - K0346+350, K0348+730 - K0348+750 | Completed | ₱12.3M |
| 25PF0027 | Apr 8, 2025 | CONSTRUCTION OF ROAD ALONG PAOAY-AGADANGAN-LAWLAWITAN, BARANGAY PALINA, KIBUNGAN, BENGUET | Completed | ₱47.8M |
| 25PF0034 | Apr 8, 2025 | REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS: GOV. BADO DANGWA NATIONAL RD - K0334 + 500 - K0334 + 525, K0334 + 575 - K0334 + 605, K0335 + 330 - K0335 + 370, K0339 + 100 - K0339 + 140, K0339+510 - K03 | On-Going | ₱52.5M |
| 25PF0042 | Apr 8, 2025 | CONSTRUCTION OF ROAD ALONG PONGO - COPCOPIT - DANGADANGAN, BAKUN, BENGUET | Completed | ₱29.0M |
| 24PF0076 | Oct 28, 2024 | CONSTRUCTION OF 2-STOREY 4 CLASSROOM SCHOOL BUILDING IN TACADANG NATIONAL HIGHSCHOOL, BARANGAY TACADANG, KIBUNGAN, BENGUET | On-Going | ₱25.4M |
| 24PF0065 | Aug 12, 2024 | INSTALLATION OF ROAD SAFETY DEVICES ALONG GOV. BADO DANGWA (PALINA-POBLACION SECTION) K0328+(-085)-K0338+731, BAKUN, BENGUET | Completed | ₱120.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.