Project 23AE0002
DPWH infrastructure contract
Contract ID:
23AE0002
Fingerprint:
2a14a255a4c2e9…0beae0b716 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 17, 2023 (3 yrs 8 mo ago) · Target/actual end Apr 3, 2023
Description:
PREVENTIVE MAINTENANCE - TERTIARY ROADS - BACNOTAN-LUNA-BALAOAN RD - K0305+000-K0305+959
Category:
Roads
Implementing office:
DPWH La Union 1st DEO · Region I
Contractor:
Contract amount:
₱9,380,495.79 (₱9.4M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 03cdc23deb66… | Jan 31, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LA UNION 1ST ED | ₱9,380,495.79 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AE0044 | May 27, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BRGY. NAPASET, LUNA, LA UNION | Completed | ₱9.1M |
| 25AE0053 | May 27, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF MULTI-PURPOSE BUILDING (SB BUILDING), BARANGAY POBLACION, LUNA, LA UNION | On-Going | ₱14.4M |
| 25AE0058 | May 26, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - COMPLETION OF MULTI-PURPOSE BUILDING, BARRIENTOS ELEMENTARY SCHOOL PAVILION, BARANGAY BARRIENTOS, LUNA, LA UNION | Completed | ₱2.9M |
| 25AE0019 | Feb 17, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY RIMOS 5, LUNA, LA UNION | Completed | ₱6.8M |
| 25AE0036 | Feb 17, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY POBLACION, LUNA, LA UNION | Completed | ₱4.8M |
| 24A00097 | Feb 26, 2024 | RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES, BOROBOR BR. (B05042LZ) ALONG MANILA NORTH RD | Completed | ₱26.8M |
| 24AE0025 | Feb 22, 2024 | CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) -REHABILITATION/ IMPROVEMENT OF RISSING TO PARATONG NO. 4 ROAD LEADING TO PARATONG DISTRICT BEACH, BANGAR, LA UNION | Completed | ₱19.3M |
| 24AE0022 | Feb 14, 2024 | CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BARANGAY NAPASET, LUNA, LA UNION | Completed | ₱83.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.