Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23AF0026

DPWH infrastructure contract
Contract ID:
23AF0026
Fingerprint:
8c28dc0d79a6f5…f7e71530b5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 31, 2023 (3 yrs 9 mo ago) · Target/actual end Jul 21, 2023
Description:
ASSET PRESRV.-REHAB/RECONST. OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRI RDS, BAUANG-BAGUIO RD K0277+263-K0277+348, BURGOS, LU
Category:
Roads
Implementing office:
Contractor:
E. E. MADAYAG CONSTRUCTION · DPWH contractor code 25029
As listed: E.E. MADAYAG CONSTRUCTION
Contract amount:
₱35,900,079.42 (₱35.9M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
eda239a61a10…Jan 26, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LA UNION 2ND ED₱35,900,079.42

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AF0114May 15, 2025CONSTRUCTION OF ROAD AT BRGY. DELLES, BURGOS, LA UNIONCompleted₱19.2M
25AF0011Mar 13, 2025CONST/IMPRVMNT OF ACCESS RDS LDNG TO DECLARED TOURISM DEST. (TOURISM ROAD INFRA PROG. -TRIP) CONST OF ACCESS ROAD LDNG TO BUDAHAW FALLS, BRGY. BILIS, BURGOS, LA UNIONCompleted₱9.8M
25AF0001Feb 25, 2025REHAB/RECONST OF ROADS W/ SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS - BAUANG-BAGUIO RD - K0278+462 - K0278+555, BURGOS, LA UNIONCompleted₱1.8M
25AF0040Feb 18, 2025REHABILITATION OF MULTI-PURPOSE BUILDING (CIVIC CENTER), BARANGAY NEW POBLACION, BURGOS, LA UNIONCompleted₱9.6M
24A00440May 13, 2024CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALILI RIVER, BARANGAY AGUIOAS, NAGUILIAN, LA UNIONCompleted₱115.8M
24AF0120Apr 18, 2024CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAUANG RIVER BASIN (PACKAGE 4), NAGUILIAN, LA UNIONCompleted₱94.6M
24AF0126Apr 18, 2024CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAUANG RIVER BASIN (PACKAGE 10), NAGUILIAN, LA UNIONCompleted₱82.4M
24AF0096Apr 16, 2024CONST./REHAB. OF FLOOD MITIGATION FACILITIES W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD CONTROL STRUC. ALONG BAUANG RIVER BASIN, BURGOS, LA UNIONCompleted₱96.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.