Project 23AH0109
DPWH infrastructure contract
Contract ID:
23AH0109
Fingerprint:
555048203ebf12…136bc1269b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 29, 2023 (3 yrs 5 mo ago) · Target/actual end Feb 2, 2024
Description:
CONCRETING OF BRGY.UYONG KULANGIT FMR,BRGY.UYONG,LABRADOR, PANGASINAN
Category:
Roads
Implementing office:
DPWH Pangasinan 2nd DEO · Region I
Contractor:
BERSON'S CONSTRUCTION & TRADING · DPWH contractor code 31181
Contract amount:
₱5,968,979.30 (₱6.0M)
Funding source:
Outside Infra - GAA 2023 DA FMR
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| bac73cf670d1… | May 22, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN 2ND | ₱5,848,477.30 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AH0158 | Jun 11, 2025 | CONSTRUCTION OF MULTI-PURPOSED BUILDING,PHASE 2,BRGY. LAOIS,LABRADOR, PANGASINAN | On-Going | ₱4.8M |
| 25A00491 | May 27, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - CLUSTER I, CONSTRUCTION OF MULTI - PURPOSE BUILDING (1. BRGY LASIP, LINGAYEN, PANGASINAN; 2. BRGY LAOIS, LABRADOR, PANGASINAN;3. BRGY BASING, BINMALEY, PANGASINAN) | On-Going | ₱29.0M |
| 25AH0078 | Mar 20, 2025 | REHAB/RECONST'N./UPGRADING OF DAMAGED PAVED ROADS-PANG.-ZAMBALES RD.-K0341+(-840)-K0341+478,K0341+53 | On-Going | ₱18.4M |
| 25AH0079 | Mar 20, 2025 | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PANG.-ZAMBALES RD.-K0341+750-K0342+32 | On-Going | ₱6.4M |
| 25AH0083 | Mar 17, 2025 | WIDENING OF PERMANENT BRIDGES AT BONGALON BR.(B02137LZ)ALONG PANGASINAN-ZAMBALES RD.(PHASE III),LABR | On-Going | ₱27.5M |
| 25AH0095 | Mar 17, 2025 | INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES(ROADWAY LIGHTING)ALONG LINGAYEN-LABRADOR DIV.RD.- | Completed | ₱43.7M |
| 25AH0087 | Feb 24, 2025 | CONSTRUCTION OF EMBANKMENT PROTECTION AT BOLO CIS,LABRADOR, PANGASINAN | On-Going | ₱14.4M |
| 25AH0099 | Feb 24, 2025 | CONSTRUCTION (COMPLETION)OF MULTI-PURPOSE BUILDING(BARANGAY HALL)BRGY. SAN GONZALO,LABRADOR, PANGASI | Completed | ₱2.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.