Project 23AI0068
DPWH infrastructure contract
Contract ID:
23AI0068
Fingerprint:
728bca63e2d4d0…8c591f7245 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 17, 2023 (3 yrs 8 mo ago) · Target/actual end Apr 26, 2023
Description:
CONSTRUCTION OF ROAD, BARANGAY SAN PABLO, BINALONAN, PANGASINAN
Category:
Roads
Implementing office:
DPWH Pangasinan 3rd DEO · Region I
Contractor:
Contract amount:
₱7,907,863.50 (₱7.9M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 84615f40397c… | Feb 1, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN 3RD DEO | ₱7,798,634.97 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AI0144 | May 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY BACAG, VILLASIS, PANGASINAN | On-Going | ₱7.7M |
| 25AI0176 | May 27, 2025 | CONSTRUCTION OF BINALONAN DIVERSION ROAD, BINALONAN, PANGASINAN | On-Going | ₱19.0M |
| 25AI0178 | May 27, 2025 | CONSTRUCTION OF ROAD SITIO BINMONTON, BRGY. STA. CATALINA, BINALONAN, PANGASINAN (PACKAGE B) | On-Going | ₱24.0M |
| 25AI0169 | Mar 28, 2025 | CONSTRUCTION OF ROAD, BINALONAN, PANGASINAN | On-Going | ₱51.5M |
| 25AI0173 | Mar 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (CIVIC CENTER), PHASE II BARANGAY SANTA MARIA NORTE, BINALONAN, PANGASINAN | On-Going | ₱48.0M |
| 25AI0049 | Mar 18, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ALORAGAT RIVER, PACKAGE 1, BINALONAN-LAOAC, PANGASINAN | Completed | ₱48.2M |
| 25AI0050 | Mar 18, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ALORAGAT RIVER, PACKAGE 2, BINALONAN-LAOAC, PANGASINAN | Completed | ₱48.2M |
| 25AI0051 | Mar 18, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ALORAGAT RIVER, PACKAGE 3, BINALONAN-LAOAC, PANGASINAN | On-Going | ₱48.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.