Project 23AI0091
DPWH infrastructure contract
Contract ID:
23AI0091
Fingerprint:
d8407fe392a44e…75e5c3101c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 31, 2023 (3 yrs 7 mo ago) · Target/actual end Apr 27, 2023
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE LOCATED AT BARANGAY SAN JOAQUIN, BALUNGAO, PANGASINAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Pangasinan 3rd DEO · Region I
Contractor:
JHI CONSTRUCTION & SUPPLY · DPWH contractor code 19317
Contract amount:
₱14,509,105.66 (₱14.5M)
Funding source:
Regular Infra - GAA 2023 CSSP
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 0e178f32c7dc… | Mar 15, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN 3RD DEO | ₱14,509,105.66 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25A00477 | Jul 4, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION / REHABILITATION OF ROADS, STA. MARIA, PANGASINAN, PHASE 3 | On-Going | ₱14.4M |
| 25AI0070 | Mar 13, 2025 | CONSTRUCTION OF RIVERBANK SLOPE PROTECTION STRUCTURE, LAGASIT RIVER, PACKAGE 1, BALUNGAO, PANGASINAN | On-Going | ₱48.5M |
| 25AI0037 | Feb 14, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGASIT RIVERS, BALUNGAO-SANTA MARIA, PANGASINAN (PANGASINAN 1) | On-Going | ₱95.2M |
| 25AI0038 | Feb 14, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGASIT RIVERS, BALUNGAO-SANTA MARIA, PANGASINAN (PANGASINAN 2) | On-Going | ₱95.5M |
| 25AI0039 | Feb 14, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGASIT RIVERS, BALUNGAO-SANTA MARIA, PANGASINAN (PACKAGE 3) | On-Going | ₱47.7M |
| 25AI0040 | Feb 14, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGASIT RIVERS, BALUNGAO-SANTA MARIA, PANGASINAN (PACKAGE 4) | On-Going | ₱47.7M |
| 25AI0041 | Feb 14, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGASIT RIVERS, BALUNGAO-SANTA MARIA, PANGASINAN (PACKAGE 5) | On-Going | ₱47.7M |
| 24AI0288 | Jan 10, 2025 | CONSTRUCTION/ REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, STA. MARIA, PANGASINAN | On-Going | ₱7.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.