FY2026 GAA: ₱6.79T
PisoScan

Project 23AI0137

DPWH infrastructure contract
Contract ID:
23AI0137
Fingerprint:
27f93b9bc142c4…b77d2101b6 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 15, 2023 (3 yrs 6 mo ago) · Target/actual end Sep 17, 2023
Description:
CONCRETING OF BRGY. CARAYACAN TO BRGY. BUENAVISTA FMR, BRGY. CARAYACAN, SAN QUINTIN AND BRGY. BUENAVISTA, UMINGAN, PANGASINAN
Category:
Roads
Implementing office:
Contractor:
RIVBROS CONSTRUCTION FACTORS & DEVELOPMENT · DPWH contractor code 28504
Contract amount:
₱11,934,839.08 (₱11.9M)
Funding source:
Outside Infra - GAA 2023 DA FMR
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
41cc68abda4b…Apr 27, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN 3RD DEO₱11,889,839.08

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AI0187Jul 18, 2025REHABILITATION OF ROAD, PHASE 1, UMINGAN, PANGASINANOn-Going₱117.0M
25AI0188Jul 18, 2025REHABILITATION OF ROAD, PHASE 2, UMINGAN, PANGASINANOn-Going₱117.0M
25A00478Jul 4, 2025BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION / REHABILITATION OF ROADS, UMINGAN, PANGASINAN, PHASE 3On-Going₱16.3M
25AI0203May 29, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 3)Completed₱48.7M
25AI0204May 29, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 4)Completed₱48.7M
25AI0205May 29, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 5)Completed₱48.7M
25AI0206May 29, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 6)Completed₱48.7M
25A00268Apr 7, 2025BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF ROAD, TAYUG, PANGASINANOn-Going₱19.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.