Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23BA0006

DPWH infrastructure contract
Contract ID:
23BA0006
Fingerprint:
4598930cca7750…71746d509d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 23, 2023 (3 yrs 7 mo ago) · Target/actual end Sep 25, 2023
Description:
ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM (OO1): ASSET PRESERVATION-CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS- TERTIARY ROADS: BASCO- MAHATO- IVANA- UYUGAN- IMNAJBU RD- K0011+566, K0011+735, K0013+262- K0013+359
Category:
Roads
Implementing office:
DPWH Batanes DEO · Region II
Contractor:
DEKM CONSTRUCTION · DPWH contractor code 32409
Contract amount:
₱2,973,400.00 (₱3.0M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1f60106b726a…Mar 9, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATANES DEO₱2,868,596.60

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26BA0005Aug 5, 2026ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM:ASSET PRESERVATION PROGRAM: REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS,SLOPE COLLAPSE,AND LANDSLIDE-TERTIARY ROADS:BASCO-MAHATAO-IVANA-UYUGAN-IMNAJBU RD-K0009+000-K0009 + 051On-Going₱27.0M
25BA0058Aug 27, 2025CSSP: BIP- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI-PURPOSE BUILDING (IVANA NATIONAL HIGH SCHOOL COVERED COURT), PHASE II, BRGY. RADIWAN, IVANA, BATANESOn-Going₱4.9M
25BA0069Aug 27, 2025CSSP: CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS- RAIN WATER COLLECTORS: CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS)Completed₱2.6M
25BA0005Aug 18, 2025OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS: BASCO- MAHATAO- IVANA- UYUGAN- IMNAJBU ROAD- K0011+760-K0011+791Completed₱48.5M
25BA0018Jun 18, 2025OO2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM:CONST./MAINT.OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS:CONST.OF SHORE PROTECTION STRUCTURE ALONG BASCO-MAHATAO-IVANA-UYUGAN-IMNAJBU ROAD,KADPIDAN SECTION,IVANA,BATANESOn-Going₱17.9M
25BA0030Jun 18, 2025BIP- PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III), CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL I), BARANGAY RADIWAN, IVANA, BATANESOn-Going₱5.8M
25BA0062Jun 18, 2025CSSP: BIP- MULTIPURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI-PURPOSE BUILDING(IVANA ELEMENTARY SCHOOL COVERED COURT),PHASE I, BRGY. RADIWAN, IVANA, BATANESCompleted₱8.2M
25BA0012Mar 17, 2025CSSP: BIP- MULTIPURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTIPURPOSE BUILDING, BRGY. RADIWAN, IVANA, BATANESOn-Going₱9.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.