Project 23BE0118
DPWH infrastructure contract
Contract ID:
23BE0118
Fingerprint:
7aa604abdc2229…bfaf2abad1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 22, 2023 (3 yrs 4 mo ago) · Target/actual end Dec 1, 2023
Description:
CONCRETING OF BRGY. CARMENCITA FMR BRGY. CARMENCITA, DELFIN ALBANO, ISABELA
Category:
Roads
Implementing office:
DPWH Isabela 1st DEO · Region II
Contractor:
DRAGON TWELVE BUILDERS AND CONSTRUCTION SUPPLY · DPWH contractor code 39808
As listed: DRAGON TWELVE BUILDERS & CONSTRUCTION SUPPLY
Contract amount:
₱11,931,928.67 (₱11.9M)
Funding source:
Outside Infra - GAA 2023 DA FMR
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 70440ca4daf9… | Jun 7, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 1ST DEO | ₱11,931,928.67 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BE0161 | Jun 17, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, RAGAN SUR NATIONAL HIGH SCHOOL, DELFIN ALBANO (MAGSAYSAY), ISABELA | On-Going | ₱3.8M |
| 26BE0010 | Jun 4, 2026 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES-CARMENCITA BR. (B04780LZ) ALONG ILAGAN-DELFIN ALBANO-MALLIG RD DELFIN ALBANO, ISABELA | On-Going | ₱29.8M |
| 25BE0106 | Jul 14, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE | On-Going | ₱93.5M |
| 25BE0125 | Jul 14, 2025 | CONCRETING OF BRGY. VILLA PAREDES TO BRGY. SAN NICOLAS FMR, BRGY. VILLA PAREDES AND BRGY. SAN NICOLAS, DELFIN ALBANO, ISABELA | On-Going | ₱14.5M |
| 25BE0031 | May 21, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - PREVENTIVE MAINTENANCE - TERTIARY ROADS - ILAGAN-DELFIN ALBANO-MALLIG RD - K0428+791 - K0430+000 DELFIN ALBANO, ISABELA | On-Going | ₱1.1M |
| 25BE0069 | May 21, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CONCRETE ROAD AT SI | On-Going | ₱14.3M |
| 25BE0070 | May 21, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CONCRETE ROAD WITH SLOPE | On-Going | ₱14.2M |
| 25BE0071 | May 21, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUTURE PROGRAM (BIP)-BIP- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG ROAD, BARANGAY | On-Going | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.