Project 23BE0149
DPWH infrastructure contract
Contract ID:
23BE0149
Fingerprint:
d9bcff7eb224e3…f3181aa7db Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 14, 2023 (3 yrs 1 mo ago) · Target/actual end Feb 13, 2024
Description:
CONSTRUCTION OF 1STY3CL, MAUI ELEMENTARY SCHOOL, DELFIN ALBANO, ISABELA
Category:
Buildings and Facilities
Implementing office:
DPWH Isabela 1st DEO · Region II
Contractor:
SMT CONSTRUCTION · DPWH contractor code 36331
Contract amount:
₱6,667,095.05 (₱6.7M)
Funding source:
Outside Infra - GAA 2023 DepEd BEFF
Budget year:
2023
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 1f7f91917354… | Aug 31, 2023 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 1ST DEO | ₱6,667,095.05 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BE0084 | Jul 14, 2025 | CONCRETING OF BUBUG FMR (PHASE I), BRGY. BUBUG, STO. TOMAS, ISABELA | On-Going | ₱14.5M |
| 25BE0109 | Jul 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF WATER SUPPLY SYSTEM AT BARANGAY BALELLENG, SANTO TOMAS, ISABELA | On-Going | ₱4.8M |
| 25BE0128 | Jul 14, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES -CONSTRUCTION OF SLOPE PROTECTION AND CROSS DRAIN ALONG BAGABAG CREEK, STO. TOMAS, ISABE | Completed | ₱14.4M |
| 25BE0091 | Jun 19, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER, PHASE 5, BARANGAY MALA | On-Going | ₱38.4M |
| 25BE0024 | Feb 26, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF CONCRETE ROAD AT BARANGAY | Completed | ₱14.7M |
| 24BE0149 | Dec 11, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD ALONG BARANGAY BUBUG | On-Going | ₱96.5M |
| 24BE0146 | Sep 5, 2024 | CONCRETING OF BRGY. BARUMBONG FMR, BRGY. BARUMBONG, STO. TOMAS, ISABELA | On-Going | ₱17.4M |
| 24BE0091 | Jun 13, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR /STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF BARANGAY BUBUG-SANTO TOMAS-QUEZON ROAD, SANTO | On-Going | ₱29.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.