Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 23BG0202

DPWH infrastructure contract
Contract ID:
23BG0202
Fingerprint:
03d0ef8bbe6e11…938192d89a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 13, 2023 (3 yrs 2 mo ago) · Target/actual end Feb 16, 2024
Description:
CONSTRUCTION OF ONE (1) STOREY TWO (2) CLASSROOM SCHOOL BUILDING WITH TOILET ATTACHED AT EACH CLASSROOM, 103627 SANTOR ELEMENTARY SCHOOL, REINA MERCEDES, ISABELA
Category:
Buildings and Facilities
Implementing office:
Contractor:
DANYSONS CONSTRUCTION AND DEVELOPMENT CORPORATION · DPWH contractor code 25452
As listed: DANYSONS CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: DANYSONS CONSTRUCTION)
Contract amount:
₱6,492,217.41 (₱6.5M)
Funding source:
Outside Infra - GAA 2023 DepEd BEFF
Budget year:
2023

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
ce8bf2ce4d85…Sep 12, 2023DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 3RD DEO₱6,492,238.32

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25BF0113Feb 2, 2026BASIC EDUCATIONAL FACILITIES FUND (BEFF) (BATCH 1) - PRIORITY SCHOOL FACILITIES AND NEW CONSTRUCTION OF CLASSROOMS, DADAP ELEMENTARY SCHOOL, LUNA, ISABELAOn-Going₱12.6M
25BF0115Feb 2, 2026BASIC EDUCATIONAL FACILITIES FUND (BEFF) (BATCH 1) PRIORITY SCHOOL FACILITIES AND NEW CONSTRUCTION OF CLASSROOMS, LUNA NATIONAL HIGH SCHOOL LUNA, ISABELACompleted₱12.6M
25BF0087Aug 4, 2025CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, BRGY. BUSTAMANTE, LUNA, ISABELAOn-Going₱2.9M
25BF0093Aug 4, 2025CONSTRUCTION OF MULTI-PURPOSE SCHOOL BUILDING, BARANGAY PUROC, LUNA, ISABELAOn-Going₱9.6M
25BF0094Aug 4, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, SCHOOL BUIDLING DAPDAP ELEMENTARY SCHOOL, BRGY. DAPDAP, LUNA, ISABELAOn-Going₱9.6M
25BF0044Jun 9, 2025BASIC INFRASTRUCTURE PROGRAM (BIP) - CONCRETING OF LOCAL ROAD, BRGY. DADAP, LUNA, ISABELAOn-Going₱4.8M
24BF0142Apr 7, 2025OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS -CONSTRUCTION OF MAGAT RIVER FLOOD CONTROL PROJECT, BARANGAY SAN ISIDRO SECTION, LUNA, ISABELACompleted₱96.5M
25BF0021Mar 17, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PUROC, LUNA, ISABELACompleted₱3.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.